Caltrans AND Supervisor Dave Potter
Invite you to ATTEND a
PUBLIC INFORMATION MEETING

For The

Rocky Creek Viaduct

DATE/TIME: FRIDAY, APRIL 12, 2013 AT 10:00 AM

LOCATION: PFEIFFER CONFERENCE ROOM AT THE BIG SUR LODGE

MEETING AGENDA
I. Welcome and Introductions
II. Project Status Update
III. Schedule
a. Compare Actual to Anticipated Progress
b. Discuss Schedule Moving Forward
i. Anticipated Completion Date for Stage 1 Construction
1. Anticipated Start Date for Stage 2 Construction
ii. Anticipated Project Completion Date
IV. Public Comments/Questions

CONTACTS:
Ken Dostalek Jayne Mohammadi
Caltrans, District 5 Aide to Supervisor Potter
Division of Project Management County of Monterey, Board of Supervisors
Ph: (805) 549-3133 Ph: (831) 647-7708
E-mail: ken.dostalek@dot.ca.gov E-mail: MohammadiJF@co.monterey.ca.us

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

Sunday Photo, 4/26/26

my first native iris this year… And a sunset taken Wednesday…

3 days ago

Sunday Photo by Della Huff

You can find more of her photographs here: https://dellahuff.smugmug.com/Big-Sur

1 week ago

Big Sur International Marathon, 4/26, Road Closure

Hello! This is a courtesy notification regarding the upcoming Big Sur International Marathon, which will take…

2 weeks ago

Ruger & Owner reunited!

5 days ago, you may recall I reported on a dog that had been left…

2 weeks ago

Lane Closure at Rocky Creek

Date:Thursday, April 16, 2026District:05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa…

2 weeks ago

This website uses cookies.