Rocky Creek Viaduct Update #28 – no closures next week

** UPDATE #28 **
HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT CONTINUES WITH DAYTIME ROADWORK AND INTERMITTENT OVERNIGHT CLOSURES

Daytime roadwork on Highway 1 at Rocky Creek continues next week from 7 am to 5 pm Monday, April 29 through Friday, May 3.

NOTE: There will be no night work or overnight closures next week—from Sunday, April 28 through Thursday, May 2.

Work next week will consist of grading the viaduct approaches.

Highway 1 at Rocky Creek has one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes at a time during daytime roadwork. Full overnight closures will be scheduled five nights a week Sundays through Thursdays, unless otherwise indicated. No overnight closures will occur on Friday/Saturday nights.

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

Sunday Photos, 5/10/26 – Happy Mother’s Day

From Heather Cox Richardson today: “If you google the history of Mother’s Day, the internet…

4 days ago

Parking at Bixby Bridge

I find the MoCo website a nightmare to navigate or I would post links to…

7 days ago

Big Sur Multi Agency Advisory Council Meeting, 5/29/26

Notice of Meeting County of Monterey Big Sur Multi-Agency Advisory Council IS HEREBY GIVEN that the Big…

1 week ago

Highway 68 and Traffic Signals

HIGHWAY 68 CORRIDOR TO MOVE TO ADAPTIVE TRAFFIC SIGNAL CONTROL BEGINNING MONDAY, MAY 4 MONTEREY…

1 week ago

Sunday Photos, 5/3/26

All photos taken at River Inn on Friday, May Day. I would rather give my…

2 weeks ago

Granite Bridge Repairs

Date:Thursday, April 30, 2026District:05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa…