Rocky Creek Viaduct Update #28 – no closures next week

** UPDATE #28 **
HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT CONTINUES WITH DAYTIME ROADWORK AND INTERMITTENT OVERNIGHT CLOSURES

Daytime roadwork on Highway 1 at Rocky Creek continues next week from 7 am to 5 pm Monday, April 29 through Friday, May 3.

NOTE: There will be no night work or overnight closures next week—from Sunday, April 28 through Thursday, May 2.

Work next week will consist of grading the viaduct approaches.

Highway 1 at Rocky Creek has one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes at a time during daytime roadwork. Full overnight closures will be scheduled five nights a week Sundays through Thursdays, unless otherwise indicated. No overnight closures will occur on Friday/Saturday nights.

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

Infrared Maps of the Plaskett Fire, 8/31 @ 10:45 pm

Plaskett, CA Wildfire Overview - 01 September 2026 c. 0545 UTC Weather Conditions - Heavy…

15 hours ago

Message from BSF Fire Chief Matt Harris

Message from your Fire Chief regarding the Timber and Plaskett Fires: This has been an…

17 hours ago

Last Combined Timber (Day 25) and Plaskett (Day 7) Morning Update, 9/1

Good Morning:  This will be the last combined Timber and Plaskett Fires Update.  Beginning this evening California…

17 hours ago

Note re Big Sur Mail from Andrew:

Good morning lovely Kate - I hope you and your structures are safe - as…

18 hours ago

Timber (Day 24) and Plaskett (Day 6) 8/31 Evening Update

Timber Fire: Fire information: (831) 285-7006 Fire email: 2026.timber@firenet.govWebsite: inciweb.wildfire.gov/incident-information/calpf-timber-fire https://inciweb.wildfire.gov/incident-information/calpf-plaskett-fire Location: Southeast of Loma Vista, Monterey CountySize:  25,190 acresStart…

1 day ago

This website uses cookies.