Subject: Nacimiento-Fergusson Construction to Begin 2/27/2017
Dear local residents and cooperators,
The anticipated construction to repair the failing section of Nacimiento-Fergusson road at MP 4.2, will begin the week of February 27, 2017.
Construction Schedule
· February 27 (Monday), the contractor will move in, set up traffic control and start construction.
· Construction will take place Monday – Saturday, weather and conditions permitting.
· This contract is for 30 days, however if conditions are right, it may take less than 3 weeks.
Road Closure
o This closure begins Monday morning February 27, 2017. The road will be open and closed during the following times:
o Open from 6:00 pm – 07:00 am and from 11:30 am – 12:00 noon. The road will also be open on Sundays.
o Closed 7:00 am – 11:30 am and from 12:00 noon – 6:00 pm. Monday through Saturday.
The contractor and the Forest Service are striving to have this project completed as soon as possible and allow traffic to safely resume use of this important road. Thank you for your patience and understanding through this challenging period.
If you have any further questions, please contact me.
Thank you,
Forest Service Shield
Debbie Evans
Roads Program Manager
Forest Service
Los Padres National Forest
Plaskett, CA Wildfire Overview - 01 September 2026 c. 0545 UTC Weather Conditions - Heavy…
Message from your Fire Chief regarding the Timber and Plaskett Fires: This has been an…
Good Morning: This will be the last combined Timber and Plaskett Fires Update. Beginning this evening California…
Good morning lovely Kate - I hope you and your structures are safe - as…
Timber Fire: Fire information: (831) 285-7006 Fire email: 2026.timber@firenet.govWebsite: inciweb.wildfire.gov/incident-information/calpf-timber-fire https://inciweb.wildfire.gov/incident-information/calpf-plaskett-fire Location: Southeast of Loma Vista, Monterey CountySize: 25,190 acresStart…
This website uses cookies.
View Comments
Thank you for providing some predictable times that we can gain access. That information makes a world of difference!
This makes passage through NF to the coast plannable. I hope a similar schedule works out for crossing Pauls.
can one reach to post office from reo road
Will it be completed this year?