Photos of Mud Creek from this weekend: 1) slip out on Friday, May 5 and top of slide on Sunday, May 7. Photo of Pfeiffer Canyon Bridge—Abutment 2 drilling from Thursday, May 4.


STATE ROUTE 1 REMAINS FULLY CLOSED IN BOTH DIRECTIONS AT MUD CREEK DUE TO CONTINUED SLIDE ACTIVITY. DELIVERY VEHICLES AND LOCAL RESIDENTS WILL NEED TO USE NACIMIENTO-FERGUSSON EXIT SOUTH OR TO CLEAR THE ACCESS TIMES AT PAUL’S SLIDE.

************************************************************************************************
· Mud Creek (PM 8.9) –NO ACCESS UNTIL FURTHER NOTICE.
·
· Mud Creek has three major issues: 1) a partial lane missing; 2) the slope/roadway is at an angle and 3) significant slide material is still coming down. Vehicles and local residents will need to use Nacimiento-Fergusson to exit south or clear the access times at Paul’s Slide.
·
Paul’s Slide (PM 21.6)—ACCESS FOR LOCAL RESIDENTS AND DELIVERY VEHICLES
ONLY.
Work on the slope continues. The targeted “public access” date of mid-June shows medium
probability with recent activity, public opening date could be pushed further out.

· 12:00PM Monday / Wednesday / Friday– A single caravan south and a single caravan north, you must be in line by noon! There may be up to 45 minute delay to clear the road before the opening.

· Delivery vehicles (Restriction is 30 feet maximum length and 50,000 lbs. maximum weight) can now use all access windows 7 days a week.

· Access times for the morning and evening are still the same except for Friday:

5:30AM to 6:00AM and 7:00PM to 7:30PM – Sat.-Thurs.

· Friday’s hours will be shortened to:

5:30AM – 8:00AM and 6:00PM to 7:30PM

· The noon opening will be for PAUL’S SLIDE ONLY, (NOT MUD CREEK); you will need to use Nacimiento-Fergusson Road to exit the coast.

Pfeiffer Canyon Bridge (PM 45.52)
The foundation pile for the abutment and wing walls was completed last week (north end) and the drilling contractor is currently mobilizing the south end to begin the foundation work there. The contractor has begun demolition of the original abutment on the north side and will be focusing on excavation, forming, placing rebar and pouring the new abutment #2 on the north side over the next few weeks.

Progress continues to take place but continued slide activity and lack of passage through Mud Creek could potentially push out public access date. Current public access date: Mid-to-late September.

Another update will be provided by mid-day Friday, May 12.

Susana Z. Cruz
Caltrans District 5
Public Information Officer
Portavoz de Relaciones Públicas
para Caltrans en el Distrito 5
805.549.3138
805.549.3326–fax
Follow us on Facebook
We welcome your feedback: https://www.surveymonkey.com/r/RNBZG55

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

Big Sur Fire Annual Muster & BBQ

Screenshot

19 hours ago

Big Sur Multiagency Advisory Council

Hello, The Big Sur Multi-Agency Advisory Council (BSMAAC) will be meeting on July 17 at 10:00am.…

2 days ago

Upcoming Marches & Events

 A Joyous Day at Pride!  Actions and Updates Hands Off Our Votes! Email comments opposing the order allowing the USPS to control…

3 days ago

Just another Monday

The Keeper Who Opened the Gates Every Monday The Jack Hopkins Now Newsletter #950: Sunday, June…

5 days ago

Sunday Photos June 28, 2026

Which do you like best? The black and white or the color?

6 days ago

Lost Hiker on South CoastI – FOUND AT SALMON CREEK

Hi Kate,  There’s a group of people heading out on the trails here around silver…

7 days ago

This website uses cookies.