Not really any changes. It still stands the Mud Creek is still closed with no anticipated date of opening; Paul’s Slide is still under 24/7 reverse traffic control; and the bridge is getting its girders – 15 total, 62 feet long, and 62 tons each. I think 3 were delivered last week.
Here are the CT photos:
I wish I could watch the whole process of the bridge going up.
The good closures map needs to be updated on https://bigsurkate.blog/big-sur-interactive-highway-maps-with-slide-names-mile-markers/
Done.