Photos: 1of Mud Creek (PM 8.9) from last Tuesday, Sept. 19, aerial courtesy of John Madonna. 2-3 of Pfeiffer Canyon Bridge (PM 45.52) showing the bridge deck pour from last Friday night, Sept. 22. Bridge deck pour video, courtesy of Kyle Evans at: https://drive.google.com/drive/folders/0B_X4C9Oiv3VvNHFvdGUxOG9GLWM

HIGHWAY 1 UPDATE – Monday, Sept. 25:

Highway 1 in Monterey County continues to provide 35 total miles of Hwy. 1 to the public from south of Gorda (PM 10) to just south of Pfeiffer Canyon (PM 45.5), accessible only via Nacimiento-Fergusson Road. State Route 1 remains closed from north of Salmon (just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek event. State Route 1 south of Salmon Creek is accessible via State Route 1 in San Luis Obispo County, past Ragged Point to Salmon Creek.

REMINDER: Travelers CANNOT travel the entire length of Highway 1 but local businesses are open on both sides of the closure points at Pfeiffer Canyon and Salmon Creek.

Mud Creek (PM 8.9)
Mud Creek had a major slide on Saturday, May 20, 2017, losing 5 million cubic yards of material. Caltrans continues with its plan to realign the existing terrain. The projected timeline to safely open to public traffic is late-summer 2018 at an estimated cost of $40 million.

There is currently no public access through the Mud Creek area since this remains an active construction zone.

Paul’s Slide (PM 21.6)
Paul’s Slide is still active but the 24/7 one-way reversing traffic control with flaggers has been replaced by a traffic signal and temporary guardrail (k-rail) in the centerline.

Pfeiffer Canyon Bridge [PCB] (PM 45.52)
The bridge construction continues with the preparation to cast the approach slab at abutment 2 (north side); setting of bridge rail posts; stripping of forms and roadway grading at Abutment 1 (south side). The opening of the new bridge is scheduled in mid-October.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information on this project and for traffic updates on other Caltrans projects in Monterey County, residents can call the District 5 toll free number at 1-831-423-0396 or can visit our website at: http://www.dot.ca.gov/dist05/paffairs/release.htm#mon.

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

View Comments

  • That is miserable, hard work- sloping around in fresh 'mud', with the noise level and a dozen men working in close quarters at night.
    History tells it that at least one worker fell into a vertical post, when they were pouring Bixby Bridge- never to be retrieved.

Share
Published by
bigsurkate

Recent Posts

No Kings Day – Sat. 10/17, both Monterey & Big Sur

NO Kings: Vote Early! Rally in Monterey, Saturday, October 17, 2-4 pm at Window on…

5 hours ago

El Niño Webinar hosted by Supervisor Kate Daniels

Community Information from Supervisor Kate Daniels: To prepare for upcoming winter weather, Supervisor Daniels will…

8 hours ago

One Way Traffic Control on Highway One Near Torre Canyon for the next 5 weeks.

Date:        Tuesday, October 13, 2026 District:   05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and…

2 days ago

Sunday Photos – a surprise find: 50 year old Life Magazine

I think my mother, god bless her, saved this for my daughter who was born…

5 days ago

This website uses cookies.