Photos: 1-3 of Mud Creek (PM 8.9) from Wednesday, Jan. 4 and Thursday, Jan. 5; photos 4-5 of Pfeiffer Canyon Bridge (PM 45.52) of AC grinding from Wednesday, Jan. 4 .

 

Everything about Mud Creek, Paul’s Slide, and the Pfeiffer Canyon Bridge remains unchanged, but additional work is:

ADDITIONAL WORK—CALPORTLAND PAVING BETWEEN LUCIA (PM 23) AND JUST SOUTH OF PCB (45.52)
Wednesday (1-10) – Grind Deli/Post office parking lot in two sections (1/2 at a time) to keep some parking spaces available.
Thursday (1-11) – Pave the Deli/Post office parking lot.
Friday (1-12) – Pave mainline Hwy 1 from PM 44.8-45.3, which is through the Deli/post office area.

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

View Comments

Recent Posts

Photo Sunday, 11/1/26, Plaskett Fire Story by Connie McCoy

Sorry, Sunday got away from me and I almost forgot this.

2 days ago

Winter Storm Preparedness Town Hall

2026-27 Winter Storm Preparedness Town Hall - Big SurTonight's meeting will be available on Zoom…

5 days ago

Reminder, Daytime closure in Torre Canyon Area tomorrow

I drove through there today and it is a bit scary. Rocks are falling in…

6 days ago

Statewide PCH & El Niño

Local News Gov. Newsom signs order to protect Pacific Coast Highway, California coastal communities from…

6 days ago

Photo Sunday, 10/25/26 – The Plaskett Fire Story, by Connie McCoy

These photos Connie took tell the story without words. I will be featuring her photos…

1 week ago

This website uses cookies.