Today’s Date: Friday, October 11, 2019
District: 05–Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa Cruz Counties
Contact: Jim Shivers or Colin Jones
Phone: (805) 549-3237 or (805) 549-3189
FOR IMMEDIATE RELEASE
HIGHWAY 1 TRAFFIC CONTROL NEAR RAGGED POINT CONTINUES NEXT WEEK/NO OVERNIGHT FULL CLOSURES PLANNED
SAN LUIS OBISPO COUNTY – A project to construct a viaduct and retaining wall on Highway 1 between the San Carpoforo Creek Bridge and Ragged Point will continue the week of Sunday Oct. 13.
Motorists will encounter one-way reversing traffic control for the installation of K-rail and a 24/7 traffic signal beginning Monday, Oct. 14 with roadwork taking place Monday through Thursday from 6 am until 6 pm and on Fridays from 6 am until 2 pm.
Electronic message boards will be posted to alert the public. This signal will allow traffic to proceed in each direction 24/7 until project completion.
No full overnight closures of Highway 1 are anticipated next week.
This $4.1 million project is Souza Engineering of San Luis Obispo, CA. It’s scheduled to be complete by Spring of 2020.
Date:Friday, July 24, 2026District:05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa Cruz…
I love a happy ending. Dog owner found and put in contact with person who…
Date: July 17, 2026 District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa…
This website uses cookies.