Overnight work on Highway One to start Sunday

Today’s Date: Friday, March 27, 2020

District:           05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa       

                         Cruz Counties                                                  

Contact:          Susana Z. Cruz Ruiz or Colin Jones

Phone:            (805) 549-3138 or (805) 549-3189

FOR IMMEDIATE RELEASE

*UPDATE*

PAVEMENT REHAB CONSTRUCTION PROJECT ALONG STATE ROUTE 1 FROM BIG SUR TO CARMEL–TEMPORARY GUARDRAIL STARTING SUNDAY NIGHT

MONTEREY COUNTY – A Caltrans pavement rehab. construction project along State Route 1 from Torre Canyon Bridge in Big Sur to just south of Carpenter Street in Carmel is underway with night time lane closures to set temporary guardrail (k-rail) at distinct locations, starting Sunday night, March 29.  The traffic impact should not exceed 10 minutes.

Overnight roadwork hours next week will be:

Sunday night, March 29: 9 pm to 6 am (next morning);

Monday through Friday night: 7 pm to 6 am (next morning).

******************************************************************************

Details on the overall project’s roadwork/closures are as follows:

Torre Canyon Bridge to Coast Rd. near Andrew Molera State Park:

  • Sundays through Mondays: 10 pm to 6 am (next morning)
  • Mondays through Thursdays: 8 am to 4 pm and 7 pm to 6 am (next morning)
  • Fridays: 8 am to 1 pm

Coast Rd. to Carmel Valley Rd.:

  • Sundays through Mondays: 10 pm to 6 am (next morning)
  • Mondays through Thursdays: 7 am to 3 pm and 7 pm to 6 am (next morning)
  • Fridays: 8 am to 1 pm and 12 midnight to 6 am (next morning)

Carmel Valley Rd. to Carpenter St.:

·         Sundays through Fridays:  9 pm to 6 am (next morning)

Slab replacement work:

·         Mondays through Thursdays:  3 pm to 6 am (next morning)

–MORE—

Roadwork consists of pavement rehab on existing roadway and guardrail replacement. Electronic message signs will be activated to inform the public about this roadwork. This roadwork is necessary for the safety of the travelling public and to protect surrounding properties.

      The contractor for this $24 million project is Granite Rock Company of San Jose, CA and

      it’s expected to be completed in the Fall of 2021.

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

Two Daytime Closures of Highway One near Torre Canyon

Date:Friday, November 6, 2026District:05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa…

2 days ago

Photo Sunday, 11/1/26, Plaskett Fire Story by Connie McCoy

Sorry, Sunday got away from me and I almost forgot this.

1 week ago

Winter Storm Preparedness Town Hall

2026-27 Winter Storm Preparedness Town Hall - Big SurTonight's meeting will be available on Zoom…

1 week ago

Reminder, Daytime closure in Torre Canyon Area tomorrow

I drove through there today and it is a bit scary. Rocks are falling in…

2 weeks ago

Statewide PCH & El Niño

Local News Gov. Newsom signs order to protect Pacific Coast Highway, California coastal communities from…

2 weeks ago

This website uses cookies.