Categories: Big Sur

Rocky Creek Repair Schedule week of 9/8

Date:Friday, September 6, 2024
District:05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa Cruz Counties
Contact:Kevin Drabinski or Genelle Padilla
Phone:(805) 549-3138 or (805) 549-3237

FOR IMMEDIATE RELEASE

UPDATE #8

INTERMITTENT DAYTIME DELAYS CONTINUE ON HIGHWAY 1 AT ROCKY CREEK

FOR WEEK OF SEPTEMBER 8

MONTEREY COUNTY – Caltrans will continue with emergency repairs to Highway 1 near the Rocky Creek Bridge, 12 miles south of Carmel. Caltrans previously stabilized and reinforced Highway 1 at this location after a March 30slipout resulted in a loss of a section of the southbound lane.

Upcoming Repair Schedule Update

For the week of Sunday September 8, daytime traffic control, customarily directed by a temporary signal, will be replaced with flagging crews from Monday September 9, thru Thursday September 12. These flagging operations are necessary to allow for the movement of trucks to deliver equipment and materials for crews as they prepare for the next phase of construction efforts. Daytime flagging will be intermittent and on an as needed basis so that construction vehicles can move in and out of the work area situated behind concrete barriers. Travelers can expect intermittent daytime delays of up to a maximum of 20 minutes.

There will be no overnight closures or delays the week of Sunday September 8, and travelers overnight will continue to enjoy access through the repair site driving on the northbound lane and directed by a temporary signal system. All Big Sur businesses and amenities remain open and accessible.

Customary Overnight Repair Schedule

Overnight work will customarily take place five nights a week, Sunday through Thursday night, and scheduled from 10 pm to 6 am. No overnight work will take place on Friday or Saturday nights.

The estimate for completion of the Rocky Creek viaduct is summer 2025 and is dependent on conditions encountered during construction. The contractor for this project is Gordon N. Ball, Inc. of Alamo, CA.

Highway 1 remains closed 40 miles south of Carmel due to the Regent’s Slide.

Road information and updates can also be found on Caltrans District 5 Social Media platforms: X/Twitter at: @CaltransD5, Facebook at: Caltrans Central Coast (District 5) and Instagram at: Caltrans_D5.

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Recent Posts

Timber Fire, Day 17, 8/24, Evening Update

CURRENT SITUATION:   Acres: 12,915   Containment: 26%   Resources Assigned:  1,417 On the northern portion of the fire around…

7 hours ago

Timber Fire, Day 17, 8/24, Morning Update

Timber Fire Update U.S. Forest Service - Los Padres National Forest Timber Fire InformationEmail: 2026.timber@firenet.gov Phone: 831-285-7006Report Release: 6:58 am on…

20 hours ago

Evacuation Orders & Warnings for the afternoon of Sun 8/23

This was from this morning s operation briefing: This is what they call their “big…

1 day ago

Timber Fire, Day 16, 8/23, Morning Update

Timber Fire Update U.S. Forest Service - Los Padres National ForestTimber Fire InformationEmail: 2026.timber@firenet.gov Phone: 831-285-7006Report Release: 7:59 am on…

2 days ago

View of Timber Fire moving Eastward

This was taken from the South Coast by Dave Nelson at 4 pm today;

2 days ago

Timber Fire, Day 15, 8/22, Evening Update

Containment has gone down, acres burned has gone up, fire is in the wilderness now…

2 days ago

This website uses cookies.