Below is an update I received today from one of the inspectors at the Rocky Creek jobsite:
—————————————————————————————————————————————————————
“CIDH piles for bents 3, 4, 5 an 6 are complete. Contractor is currently working at bent 2 pile. The average production rate for the piles is still approximately 1 pile per week. However, bent 2 pile may take longer as drilling can only be performed during the night under full closure due to space constrains. Placement of the piles is on schedule.”
————————————————————————————————————————————————————–
I have attached a photo below that illustrates this information:
(See attached file: Updated drilling locations.JPG)
Also, I’m going to be on a Monterey TV program tomorrow discussing the Rocky Creek project as well as the Pitkins Rock Shed project. Not sure if you can get this program where you are but I thought I’d mention it. Below is a link to more information.
http://montereytelevision.com/YourTown.htm
Have a good day!
Ken
Also, here is a photo of a bridge showing the part labeled “the bent.”
FOREST ORDER NO. 05-07-51-26-03USDA FOREST SERVICELOS PADRES NATIONAL FORESTSAN CARPOFORO BEACH OVERNIGHT CAMPING AND CAMPFIRE…
The US Forest Service (USFS) and National Park Service (NPS) are facing severe threats from…
Given the US situation, the economy, and the world situation, it might not be the…
This is from a member of the BigSurKate community. She shared it with me and…
This website uses cookies.