Below is an update I received today from one of the inspectors at the Rocky Creek jobsite:
—————————————————————————————————————————————————————
“CIDH piles for bents 3, 4, 5 an 6 are complete. Contractor is currently working at bent 2 pile. The average production rate for the piles is still approximately 1 pile per week. However, bent 2 pile may take longer as drilling can only be performed during the night under full closure due to space constrains. Placement of the piles is on schedule.”
————————————————————————————————————————————————————–
I have attached a photo below that illustrates this information:
(See attached file: Updated drilling locations.JPG)
Also, I’m going to be on a Monterey TV program tomorrow discussing the Rocky Creek project as well as the Pitkins Rock Shed project. Not sure if you can get this program where you are but I thought I’d mention it. Below is a link to more information.
http://montereytelevision.com/YourTown.htm
Have a good day!
Ken
Also, here is a photo of a bridge showing the part labeled “the bent.”
Date:Friday, November 6, 2026District:05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa…
Sorry, Sunday got away from me and I almost forgot this.
2026-27 Winter Storm Preparedness Town Hall - Big SurTonight's meeting will be available on Zoom…
I drove through there today and it is a bit scary. Rocks are falling in…
Local News Gov. Newsom signs order to protect Pacific Coast Highway, California coastal communities from…
This website uses cookies.