Below is an update I received today from one of the inspectors at the Rocky Creek jobsite:
—————————————————————————————————————————————————————
“CIDH piles for bents 3, 4, 5 an 6 are complete. Contractor is currently working at bent 2 pile. The average production rate for the piles is still approximately 1 pile per week. However, bent 2 pile may take longer as drilling can only be performed during the night under full closure due to space constrains. Placement of the piles is on schedule.”
————————————————————————————————————————————————————–
I have attached a photo below that illustrates this information:
(See attached file: Updated drilling locations.JPG)
Also, I’m going to be on a Monterey TV program tomorrow discussing the Rocky Creek project as well as the Pitkins Rock Shed project. Not sure if you can get this program where you are but I thought I’d mention it. Below is a link to more information.
http://montereytelevision.com/YourTown.htm
Have a good day!
Ken
Also, here is a photo of a bridge showing the part labeled “the bent.”
Yesterday, Tuesday June 16, 2026, I had the pleasure of being a passenger down the…
In honor of a certain birthday today taken one year ago, I offer:
From NOAA and the National Weather Service . Collectively, the coupled ocean-atmosphere system reflected the…
Date: June 5, 2026 District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and…
No campfires outside of designated campsites and day use areas listed in Appendix A below:…
This website uses cookies.