Rocky Creek Viaduct update with photos

Below is an update I received today from one of the inspectors at the Rocky Creek jobsite:

—————————————————————————————————————————————————————
“CIDH piles for bents 3, 4, 5 an 6 are complete. Contractor is currently working at bent 2 pile. The average production rate for the piles is still approximately 1 pile per week. However, bent 2 pile may take longer as drilling can only be performed during the night under full closure due to space constrains. Placement of the piles is on schedule.”
————————————————————————————————————————————————————–

I have attached a photo below that illustrates this information:

(See attached file: Updated drilling locations.JPG)

Also, I’m going to be on a Monterey TV program tomorrow discussing the Rocky Creek project as well as the Pitkins Rock Shed project. Not sure if you can get this program where you are but I thought I’d mention it. Below is a link to more information.

http://montereytelevision.com/YourTown.htm

Have a good day!

Ken

Also, here is a photo of a bridge showing the part labeled “the bent.”

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

No Kings Day – Sat. 10/17, both Monterey & Big Sur

NO Kings: Vote Early! Rally in Monterey, Saturday, October 17, 2-4 pm at Window on…

3 days ago

El Niño Webinar hosted by Supervisor Kate Daniels

Community Information from Supervisor Kate Daniels: To prepare for upcoming winter weather, Supervisor Daniels will…

3 days ago

One Way Traffic Control on Highway One Near Torre Canyon for the next 5 weeks.

Date:        Tuesday, October 13, 2026 District:   05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and…

5 days ago

Sunday Photos – a surprise find: 50 year old Life Magazine

I think my mother, god bless her, saved this for my daughter who was born…

1 week ago

This website uses cookies.