Rocky Creek Viaduct update with photos

Below is an update I received today from one of the inspectors at the Rocky Creek jobsite:

—————————————————————————————————————————————————————
“CIDH piles for bents 3, 4, 5 an 6 are complete. Contractor is currently working at bent 2 pile. The average production rate for the piles is still approximately 1 pile per week. However, bent 2 pile may take longer as drilling can only be performed during the night under full closure due to space constrains. Placement of the piles is on schedule.”
————————————————————————————————————————————————————–

I have attached a photo below that illustrates this information:

(See attached file: Updated drilling locations.JPG)

Also, I’m going to be on a Monterey TV program tomorrow discussing the Rocky Creek project as well as the Pitkins Rock Shed project. Not sure if you can get this program where you are but I thought I’d mention it. Below is a link to more information.

http://montereytelevision.com/YourTown.htm

Have a good day!

Ken

Also, here is a photo of a bridge showing the part labeled “the bent.”

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

Granite Bridge Repairs

Date:Thursday, April 30, 2026District:05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa…

2 hours ago

Sunday Photo, 4/26/26

my first native iris this year… And a sunset taken Wednesday…

4 days ago

Sunday Photo by Della Huff

You can find more of her photographs here: https://dellahuff.smugmug.com/Big-Sur

2 weeks ago

Big Sur International Marathon, 4/26, Road Closure

Hello! This is a courtesy notification regarding the upcoming Big Sur International Marathon, which will take…

2 weeks ago

Ruger & Owner reunited!

5 days ago, you may recall I reported on a dog that had been left…

2 weeks ago

This website uses cookies.