Rocky Creek Viaduct update with photos

Below is an update I received today from one of the inspectors at the Rocky Creek jobsite:

—————————————————————————————————————————————————————
“CIDH piles for bents 3, 4, 5 an 6 are complete. Contractor is currently working at bent 2 pile. The average production rate for the piles is still approximately 1 pile per week. However, bent 2 pile may take longer as drilling can only be performed during the night under full closure due to space constrains. Placement of the piles is on schedule.”
————————————————————————————————————————————————————–

I have attached a photo below that illustrates this information:

(See attached file: Updated drilling locations.JPG)

Also, I’m going to be on a Monterey TV program tomorrow discussing the Rocky Creek project as well as the Pitkins Rock Shed project. Not sure if you can get this program where you are but I thought I’d mention it. Below is a link to more information.

http://montereytelevision.com/YourTown.htm

Have a good day!

Ken

Also, here is a photo of a bridge showing the part labeled “the bent.”

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

Happy Thanksgiving

I am thankful for all my family and friends who enrich my life and being.…

2 days ago

Full Daytime Closures of Highway 1 near Torre Canyon to take place Dec 9th and 10th

Date:Tuesday, November 24, 2026District:05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa…

4 days ago

Big Sur Information

Introduction to Big Sur information.

4 days ago

Plaskett Fire Aftermath, by Connie McCoy

OLYMPUS DIGITAL CAMERA

6 days ago

Gotcha Day, 11/21/19

7 years ago today — I took in this baby,…My bundle of constantly shedding joy.…

1 week ago

This website uses cookies.