Below is an update I received today from one of the inspectors at the Rocky Creek jobsite:
—————————————————————————————————————————————————————
“CIDH piles for bents 3, 4, 5 an 6 are complete. Contractor is currently working at bent 2 pile. The average production rate for the piles is still approximately 1 pile per week. However, bent 2 pile may take longer as drilling can only be performed during the night under full closure due to space constrains. Placement of the piles is on schedule.”
————————————————————————————————————————————————————–
I have attached a photo below that illustrates this information:
(See attached file: Updated drilling locations.JPG)
Also, I’m going to be on a Monterey TV program tomorrow discussing the Rocky Creek project as well as the Pitkins Rock Shed project. Not sure if you can get this program where you are but I thought I’d mention it. Below is a link to more information.
http://montereytelevision.com/YourTown.htm
Have a good day!
Ken
Also, here is a photo of a bridge showing the part labeled “the bent.”
Memorial Day, the unofficial beginning of the summer tourist season is almost upon us. Tuesday…
.Big Sur is used to landslides, but having two back to back which closed the…
Central Coast, Stand Up! 📣 Join us at a town hall to learn what proposed…
There are some really interesting charts provided for this. If you want to check it…
From Heather Cox Richardson today: “If you google the history of Mother’s Day, the internet…
This website uses cookies.