Photo by Andrew Borrelli, CalTrans inspector.
Yesterday, Rock Knocker was able to drive across the bridge and called me very excited. He won’t get his photos to me until Saturday, at which time I will post them, if possible.
Today, CalTrans released this:
“District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa
Cruz Counties
Contact: Susana Z Cruz (bilingual) or Colin Jones
Phone: (805) 549-3138 or 549-3189
FOR IMMEDIATE RELEASE
HIGHWAY 1/PITKINS CURVE BRIDGE AND ROCKSHED PROJECT CONTINUES
MONTEREY COUNTY—A permanent slide repair project which began in December 2009 to construct a bridge, rockshed and a retaining wall at Hwy. 1/Pitkins Curve will now allow one lane of traffic to drive on the new bridge as of yesterday, March 19, Caltrans officials have announced.
The ¼ mile project limits are from just north of Limekiln Creek Bridge to south of Lucia. Roadwork is currently being done with one-way traffic control and a signal in operation 24/7. The project includes a rockshed, a bridge, and a retaining wall.
“We are excited to provide limited traffic on the new bridge as project completion nears,” said District 5 Director Tim Gubbins. The entire project is scheduled to be done this fall.”
My sources say a ribbon-cutting ceremony is planned for early August.
This is a reminder that your input is needed! The CHMP survey will close at…
Summer Solstice June 21, 2023 AFP VIA GETTY IMAGES Screenshot
Yesterday, Tuesday June 16, 2026, I had the pleasure of being a passenger down the…
In honor of a certain birthday today taken one year ago, I offer:
From NOAA and the National Weather Service . Collectively, the coupled ocean-atmosphere system reflected the…
This website uses cookies.