Subject: Nacimiento-Fergusson Construction to Begin 2/27/2017

Dear local residents and cooperators,

The anticipated construction to repair the failing section of Nacimiento-Fergusson road at MP 4.2, will begin the week of February 27, 2017.

Construction Schedule
· February 27 (Monday), the contractor will move in, set up traffic control and start construction.
· Construction will take place Monday – Saturday, weather and conditions permitting.
· This contract is for 30 days, however if conditions are right, it may take less than 3 weeks.

Road Closure
o This closure begins Monday morning February 27, 2017. The road will be open and closed during the following times:
o Open from 6:00 pm – 07:00 am and from 11:30 am – 12:00 noon. The road will also be open on Sundays.
o Closed 7:00 am – 11:30 am and from 12:00 noon – 6:00 pm. Monday through Saturday.

The contractor and the Forest Service are striving to have this project completed as soon as possible and allow traffic to safely resume use of this important road. Thank you for your patience and understanding through this challenging period.

If you have any further questions, please contact me.

Thank you,

Forest Service Shield
Debbie Evans
Roads Program Manager
Forest Service
Los Padres National Forest

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

View Comments

Share
Published by
bigsurkate

Recent Posts

Trail Fire — Botcher’s Gap

Currently there are both ground units and air tankers on this fire. “Approx 2 acres…

2 days ago

Caltrans lack of response to invasive species brought in by contractors

Dave Nelson, and others have been trying to get Caltrans to address their contributions to…

2 days ago

Fundraiser for Big Sur

Brought to you by: Community Foundation of Monterey County. Further details can be found: https://give.cfmco.org/event/fundraiser-for-big-sur/e582609…

3 days ago

Caltrans opens Twice Daily Rocky Creek Convoy to the Public starting tomorrow, 4/29

UPDATE #15 CALTRANS EXTENDS ROCKY CREEK CONVOY TO THE PUBLIC BEGINNING MONDAY, APRIL 29 MONTEREY…

4 days ago

Community Meeting re the Rural Community Center Zoning Districts – POSTPONED TO 6/18

The County of Monterey Housing and Community Development Department staff invites you to attend a…

6 days ago