Not really any changes. It still stands the Mud Creek is still closed with no anticipated date of opening; Paul’s Slide is still under 24/7 reverse traffic control; and the bridge is getting its girders – 15 total, 62 feet long, and 62 tons each. I think 3 were delivered last week.
Here are the CT photos:
Date:Friday, November 6, 2026District:05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa…
Sorry, Sunday got away from me and I almost forgot this.
2026-27 Winter Storm Preparedness Town Hall - Big SurTonight's meeting will be available on Zoom…
I drove through there today and it is a bit scary. Rocks are falling in…
Local News Gov. Newsom signs order to protect Pacific Coast Highway, California coastal communities from…