No changes in the 3 closures – Paul’s slide 24/7 flagging; Mud Creek building wall; and Bridge on track for mid to late September opening. Here are the photos:

Photos of: 1-2) Mud Creek (PM 8.9) Construction of the seatrain rock fall barrier is complete; construction of the rock revetment continues at the north beach, which will protect the fill below the new highway alignment. Work on the northern cut above the north beach is halted until the rock revetment work is completed. Photo and Video of 3-4) Pfeiffer Canyon Bridge (PM 45.52) No video, as I have not added that feature which is yet another upgrade to my plan.

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

View Comments

Share
Published by
bigsurkate

Recent Posts

Big Sur Information

Introduction to Big Sur information.

5 days ago

Big Sur Winter Preparedness & South Coast Zoom Meeting 11/19 info

Please see the message below from Supervisor Kate Daniels. It includes a comprehensive list of…

5 days ago

Big Sur Fire Survey

For more than 50 years, Big Sur Fire's volunteer firefighters have answered the call for…

5 days ago

Veteran’s Day, 2026

Dear Ms. Novoa,On this Veterans Day, we proudly celebrate the extraordinary women and men who have…

6 days ago

Get Ready for El Niño 2026

This is the current list of Winter Storm Town Hall Meetings. Also, at the last…

1 week ago

This website uses cookies.