No changes in the 3 closures – Paul’s slide 24/7 flagging; Mud Creek building wall; and Bridge on track for mid to late September opening. Here are the photos:
Photos of: 1-2) Mud Creek (PM 8.9) Construction of the seatrain rock fall barrier is complete; construction of the rock revetment continues at the north beach, which will protect the fill below the new highway alignment. Work on the northern cut above the north beach is halted until the rock revetment work is completed. Photo and Video of 3-4) Pfeiffer Canyon Bridge (PM 45.52) No video, as I have not added that feature which is yet another upgrade to my plan.
This is from a member of the BigSurKate community. She shared it with me and…
To our beloved community, Thank you so much for your outpouring of love and care…
In case you missed it a few days ago when I posted the MoCo protest…
Count down to No Kings 3!!!!! We are officially on top of the map for…
This website uses cookies.
View Comments
Will do!! Be safe.
Sent from my iPhone
>
Check out John Osumi's (Bishop Peak Technology) photo of Mud Slide from above: https://www.facebook.com/photo.php?fbid=10103307994524315&set=pcb.10103308001195945&type=3&theater. It really shows all of the road work that's been done!