Highway 1 closure update, 12/18/17

Photos: 1-3 of Mud Creek (PM 8.9) from Wednesday, Dec. 13 ; photos 4-6 of Pfeiffer Canyon Bridge (PM 45.52) from Monday, Dec. 11 .

HIGHWAY 1 UPDATE – Monday, Dec. 18
State Route 1 in Monterey County remains closed from north of Salmon Creek, just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek slide. State Route 1 south of Salmon Creek is accessible via State Route 1 in San Luis Obispo County near Ragged Point.

REMINDER: Travelers still CANNOT access the entire length of Highway 1 from Carmel to Cambria but local businesses are open on both sides of Mud Creek.

Mud Creek (PM 8.9)
Mud Creek had a major slide on Saturday, May 20, 2017, losing over 5 million cubic yards of material. Caltrans continues with its plan to realign the existing terrain with the projected timeline to safely open to public traffic is late-summer 2018 at an estimated cost of $40 million.

Last week, the contractor continued placing rock revetment, working from the north going south and will place rock revetment across the entire toe. Also, construction continues of the south fill embankment. These same operations will continue this week.

There is currently no public/local access through the Mud Creek area since this remains an active, emergency construction zone.

Paul’s Slide (PM 21.6)
Paul’s Slide is still active but the 24/7 traffic signal remains in place and temporary guardrail (k-rail) in the centerline.

Pfeiffer Canyon Bridge [PCB] (PM 45.52)
Final work continues for several weeks. Roadwork at Pfeiffer Canyon Bridge consists of alternating lane closures from 7 am to 4 pm Mondays through Thursdays and 7 am to 2 pm on Fridays until work is complete. Last week the contractor continued with prep and painting on the girders; installed the joint seal assemblies; performed permanent seeding and mulching, and completed the underground electrical for the seismic sensors. This week, the contractor will continue painting the girders, finish permanent seeding, remove concrete debris in turnout south of the project, and perform concrete finishing on structure—activities this week will require lane closures, as mentioned above.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

The next update will be on Wednesday, Dec. 27. Happy Holidays to all!!! ☺
Susana Z. Cruz nature-flower-blue-motif[1]

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

Big Sur on a Tuesday in June

Yesterday, Tuesday June 16, 2026, I had the pleasure of being a passenger down the…

4 days ago

Sunday Photos June 14th 2026

In honor of a certain birthday today taken one year ago, I offer:

7 days ago

El Niño Predictions

From NOAA and the National Weather Service . Collectively, the coupled ocean-atmosphere system reflected the…

1 week ago

Sunday Photos 6/7/26

This was taken after the last rains.

2 weeks ago

Road Work Next Week on Highway One in Big Sur

Date:        June 5, 2026  District:     05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and…

2 weeks ago

Fire Restrictions begin tomorrow, 6/4/26 in the LPNF

No campfires outside of designated campsites and day use areas listed in Appendix A below:…

2 weeks ago

This website uses cookies.