Highway 1 closure update, 12/18/17

DF0F9BBB-22D9-4701-8402-BCEBFC098024EE59818B-570E-4C6D-A59A-11C5ED3B285CC5634C30-298A-4663-85A7-D6EC6F558FF0CA67C448-6BD2-4F7D-A8B4-789719253E8FDBED83FB-AA5E-4B5E-9784-708F4A37A8C6E1783761-476F-4F0E-AB83-0CEF146C977D

Photos: 1-3 of Mud Creek (PM 8.9) from Wednesday, Dec. 13 ; photos 4-6 of Pfeiffer Canyon Bridge (PM 45.52) from Monday, Dec. 11 .

HIGHWAY 1 UPDATE – Monday, Dec. 18
State Route 1 in Monterey County remains closed from north of Salmon Creek, just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek slide. State Route 1 south of Salmon Creek is accessible via State Route 1 in San Luis Obispo County near Ragged Point.

REMINDER: Travelers still CANNOT access the entire length of Highway 1 from Carmel to Cambria but local businesses are open on both sides of Mud Creek.

Mud Creek (PM 8.9)
Mud Creek had a major slide on Saturday, May 20, 2017, losing over 5 million cubic yards of material. Caltrans continues with its plan to realign the existing terrain with the projected timeline to safely open to public traffic is late-summer 2018 at an estimated cost of $40 million.

Last week, the contractor continued placing rock revetment, working from the north going south and will place rock revetment across the entire toe. Also, construction continues of the south fill embankment. These same operations will continue this week.

There is currently no public/local access through the Mud Creek area since this remains an active, emergency construction zone.

Paul’s Slide (PM 21.6)
Paul’s Slide is still active but the 24/7 traffic signal remains in place and temporary guardrail (k-rail) in the centerline.

Pfeiffer Canyon Bridge [PCB] (PM 45.52)
Final work continues for several weeks. Roadwork at Pfeiffer Canyon Bridge consists of alternating lane closures from 7 am to 4 pm Mondays through Thursdays and 7 am to 2 pm on Fridays until work is complete. Last week the contractor continued with prep and painting on the girders; installed the joint seal assemblies; performed permanent seeding and mulching, and completed the underground electrical for the seismic sensors. This week, the contractor will continue painting the girders, finish permanent seeding, remove concrete debris in turnout south of the project, and perform concrete finishing on structure—activities this week will require lane closures, as mentioned above.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

The next update will be on Wednesday, Dec. 27. Happy Holidays to all!!! ☺
Susana Z. Cruz nature-flower-blue-motif[1]

~ by bigsurkate on December 18, 2017.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

 
%d bloggers like this: