TAMC report for next week

MONTEREY COUNTY – Here are the major scheduled road and lane closures for Monterey County from Sunday, August 18 through Saturday, August 24 – newest information is in red.Please keep in mind that construction work is weather-dependent. 

Highway 1: Ragged Point, Big Sur: August – September  
Highway 1 will be closed from north of the San Carpoforo Creek Bridge to south of the Ragged Point Inn during the evenings from 9 pm until 5 amThese overnight FULL highway closures will occur, Sunday night through Friday morning to allow for the construction of the foundation of a viaduct. Emergency vehicles and local residents will maintain access during these overnight closures. Motorists will also encounter one-way reversing traffic control within the project limits,  Monday – Friday, from 5 am –  until 4 pm.

Highway 1: San Luis Obispo County Line – Lime Creek Bridge, Big Sur:  Aug.19– Aug.22   
One lane closure and one-way traffic controls will be in place along northbound and southbound Highway 1 between the San Luis Obispo County Line and Lime Creek Bridge for mowing work from 7 a.m. to 4 p.m.

Highway 1: Bixby Creek Bridge – Hurricane Point: August 19 – August 21  
One – way traffic controls will be in place on northbound and southbound Highway 1 between  the Bixby Creek Bridge and Hurricane Point for slope repair work along the highway from 6 a.m. to 3 p.m.

Highway 1: Rocky Creek Viaduct –  Hurricane Point: August 22 – August 23  
One – way traffic controls will be in place on northbound and southbound Highway 1 between  the Rocky Creek Viaduct and Hurricane Point for guardrail repair work along the highway from 6 a.m. to 3 p.m.

Highway 1: Carmel – Santa Cruz County Line: August 18 – August 24
Alternating lane closures and intermit ramp closures will occur along northbound and southbound Highway 1 between Carpenter Street in Carmel and the Santa Cruz County Line for striping work on the road and ramps; and one-way traffic controls will be in place on portions of the highway between Highway 156, the Elkhorn Slough Bridge and the Santa Cruz County Line, in the evenings, Sunday  – Thursday, from 9 p.m. to 6 a.m.

Highway 68: Pacific Grove – Monterey: August 20 – August 23   
One nighttime lane closure and one-way traffic controls will be in place along eastbound and westbound Highway 68 between Piedmont Avenue and Highway 1 for drainage work in the evenings, Tuesday – Thursday, from 8 p.m. to 6 a.m.

Highway 101: East Market Street – Boronda Road, Salinas: July 23 – August 22   
Full-time ramp closures will occur along northbound and southbound Highway 101 between East Market Street and Boronda Road for the first phase of ramp reconstruction work at the following locations beginning Tuesday, July 23 through Thursday, August 22:

  • The northbound US 101 off-ramp to North Main Street will be closed Tuesday, July 23 through Monday, August 12.  Motorists may detour by using West Laurel Drive to North Main Street.
  • The southbound US 101 off-ramp to East Market Street will be closed beginning Monday, July 29 through Friday, August 16. Motorists may use John Street to northbound US 101 to the off-ramp at East Market Street.
  • The northbound US 101 on-ramp at North Main Street will be closed beginning Friday, August 2 through Thursday, August 22. Motorists may detour by continuing on North Main Street to West Laurel Drive to northbound US 101

Highway 101: Alta Street/Old Stage Road – Little Bear Creek Bridge, Salinas: Aug. 18 – 23  
Nighttime lane closures will occur along northbound and southbound Highway 101 between Alta Street/Old Stage Road and Little Bear Creek Bridge in Salinas for paving work on the roadway and ramps from 7 p.m. to 6 a.m.    

Highway 101: Broadway Street  – Jolon Road, King City: August 19 – August 22
One lane closure and full ramp closures will occur northbound and southbound Highway 101 in King City between Broadway Street and Jolon Road for survey work from 7 a.m. to 4 p.m.

Highway 101: San Antonio River Bridge: August 20
One lane closure will occur  along northbound Highway 101 at the San Antonio River Bridge in King City for tree work from 9 a.m. to 1 p.m.

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

Share
Published by
bigsurkate

Recent Posts

Traffic Light to be installed at Rocky Creek Bridge

Note: the current expectation is that this light will be active thru the 2028 Big…

4 days ago

Memorial Day, 2026

To all those who made the ultimate sacrifice for our county, and an apology for…

6 days ago

Photo Sunday, 5/24/26

Not really a photo, but I like this. Created by See Monterey. Slogan by Kate…

7 days ago

Official County Statement re Parking at Bixby Bridge

Monterey County Board of Supervisors Fact Sheet: Bixby Bridge Parking Moratorium Meeting Date: Tuesday, May…

1 week ago

Nightmare at Bixby…coming to a screen near you

Memorial Day, the unofficial beginning of the summer tourist season is almost upon us. Tuesday…

1 week ago

This website uses cookies.