PRESS RELEASE
RIO ROAD
RESURFACING PROJECT
PROJECT NO. 450002
The County of Monterey will commence the Rio Road Resurfacing Project between Atherton Road and
Birch Place on April 21, 2026.
The project is scheduled to take 2 days to complete.
Work Schedule:
April 22, 2026
• Removal of existing Striping on Rio Road between Atherton Road and Birch Place.
• Removal of damaged roadway surface & replace it with Hot Mix Asphalt in various locations
• Access to residences may be temporarily impacted during the construction hours
between 8:00 PM and 5:00 AM and should expect 10-minute delays.
April 23, 2026
• Placement of Micro Surfacing along the entire length of a Rio Rd from Atherton Rd and Birch Place.
• Access to residences may be temporarily impacted during the construction hours between 8:00
PM and 5:00 AM and should expect delays.
• Residents are encouraged to park in alternate locations in advance.
• Emergency access will be permitted through the construction zone as needed.
This project is funded by Measure AA, with an estimated construction cost of approximately $350,000.
Graniterock Construction is the prime contractor for this project.
For more information, please contact:
Billy Issa, Project Mana
July 3rd, 2008 is when it started, after 5 pm on a holiday weekend, not…
Hello, The Big Sur Multi-Agency Advisory Council (BSMAAC) will be meeting on July 17 at 10:00am.…
A Joyous Day at Pride! Actions and Updates Hands Off Our Votes! Email comments opposing the order allowing the USPS to control…
The Keeper Who Opened the Gates Every Monday The Jack Hopkins Now Newsletter #950: Sunday, June…
This website uses cookies.