Highway Closure Update, 4/30/18

Here is the relevant info re Mud Creek and Paul’s Slide. The rest is pretty much the same:

Mud Creek (PM 8.9)

Mud Creek had a major slide on Saturday, May 20, 2017, losing over 5 million cubic yards of material. Caltrans continues with its plan to realign the existing terrain. The Department has announced a new target of mid-September to get lanes re-opened to traffic. Caltrans will continuously evaluate the opening date as work progresses so we anticipate providing an update in July. It’s expected that even after the highway is re-open, intermittent lane closures and roadwork may continue. The updated current cost is at $54 million.

This week: Work continues on the north cut, middle and north fills, and on north berm.

There is currently no public/local access through the Mud Creek area since this remains an active, emergency construction zone.

Paul’s Slide (PM 21.6)

Paul’s Slide was cleaned up last week from debris and slide material. It is still active but the 24/7traffic signal remains in place and temporary guardrail.

bigsurkate

Appointed appellate counsel for indigent defendants (retired.) I have lived in Big Sur since 1984, first on the north coast, and on the South Coast since 1989.

View Comments

Share
Published by
bigsurkate

Recent Posts

Fire Restrictions begin tomorrow, 6/4/26 in the LPNF

No campfires outside of designated campsites and day use areas listed in Appendix A below:…

5 hours ago

Sunday Photo, 5/31/26

(c)Kate Novoa Matt Moberg I think every human being  eventually has a moment where they…

4 days ago

Traffic Light to be installed at Rocky Creek Bridge

Note: the current expectation is that this light will be active thru the 2028 Big…

1 week ago

Memorial Day, 2026

To all those who made the ultimate sacrifice for our county, and an apology for…

1 week ago

Photo Sunday, 5/24/26

Not really a photo, but I like this. Created by See Monterey. Slogan by Kate…

2 weeks ago

This website uses cookies.