HIGHWAY 1/PITKINS CURVE BRIDGE AND ROCKSHED PROJECT—THREE OVERNIGHT CLOSURES STARTING SUNDAY, NOV. 24

MONTEREY COUNTY — The Highway 1 Bridge and Rockshed at Pitkin’s Curve (post-mile 21.5) will be closing for three nights, starting Sunday, Nov. 24, Caltrans officials announced today.

Overnight work hours/closures will be from 10 pm to 6 am Sunday night Nov. 24, Monday, Nov. 25, and Tuesday, Nov. 26 (opening on Wednesday, Nov. 27 at 6 am)

A full closure is needed to allow for the installation of the bridge joint seal assemblies. Only emergency vehicles will be allowed through. Flaggers will be present at each end of the project enforcing the closure. Detour consists of using Hwy. 46/Hwy. 101/Hwy. 68.

The ¼ – mile project limits extends from just north of Limekiln Creek Bridge to south of Lucia. The project includes a rockshed, a bridge, and a retaining wall.

“We are excited to see this project approaching completion,” said Caltrans District 5 Director Tim Gubbins. The entire project is scheduled to be completed in January, weather permitting.

Rain Report, 11/21/13