Date: | Friday, June 23, 2023 |
District: | 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa Cruz Counties |
Contact: | Kevin Drabinski or Alexa Bertola |
Phone: | (805) 549-3138 or (805) 549-3237 |
FOR IMMEDIATE RELEASE
UPDATE #43
NORTHERN CLOSURE OF HIGHWAY 1 MOVED SOUTH TO LUCIA
REPAIRS TO CONTINUE AT DANI CREEK AND PAUL’S SLIDE
MONTEREY / SAN LUIS OBISPO COUNTIES – The northern closure of Highway 1 on the Big Sur coast moved four miles south today, from the Big Creek Vista Point in Monterey County at Post Mile 27.3 to Lucia at PM 23.2.
With this move of the northern closure, a roughly two-mile stretch of Hwy. 1 remains closed to through traffic.
Travelers in the Monterey area will now be able to travel approximately 55 miles south on Hwy. 1 before encountering the turnaround at Lucia.
The southern closure of Hwy. 1 remains located at just before the entrance to Limekiln State Park at PM 21.2. Limekiln State Park remains closed to the public.
Travelers in the Morro Bay – Cambria area will be able to travel north for over 47 miles from Cambria on Hwy. 1 until they encounter the turnaround at Limekiln State Park. All coastal businesses remain open.
Repairs to a major slip out at Dani Creek at PM 22.6 continue. Crews have removed debris from the slip out area below the roadway and have been reconstructing the highway embankment which is approaching the previous level of the road. Crews will next focus on a tunneling operation which will drive a culvert through the fill below the roadway. Repairs at Dani Creek are expected to continue through August 17.
Crews are also continuing to work 12-hour shifts, seven days a week, at Paul’s Slide at PM 21.7. The current estimate for reopening the highway at Paul’s Slide is still several months. A refreshed estimate for a reopening date at Paul’s Slide will be made in mid-July.
Road information and updates can also be found on Caltrans District 5 Social Media platforms: Twitter at: @CaltransD5, Facebook at: Caltrans Central Coast (District 5) and Instagram at: Caltrans_D5.
Our crews deserve to get home safely too.
Drive slowly and carefully in work zones.
CHP Traffic Incident Information Page: http://cad.chp.ca.gov
View of eastern side of Highway 1 at Dani Creek showing reconstruction of highway embankment and staging for tunneling operations which will drive a culvert through the fill below the roadway.
Traveler information at: https://quickmap.dot.ca.gov/
###
Kevin Drabinski
Public Information Officer
Caltrans District 5
50 Higuera St.
San Luis Obispo CA 93401
Office: 805.549.3138
Cell: 805.748.1858
TTY 711