Bridge Progress by Kyle Evans

Bridge Photos from 9/11/2017 (The bridge will be slightly further along now then when I was down there on Monday but no major changes happened since then)

I went down to the bridge to check on the progress and get some updates.

The project is moving along very nicely. The crew is sticking to a mid October opening and working very hard to get it done as fast and as safely as possible.

The rebar across the deck is almost done. This also includes bolts in place that will be used to attach the guard rails. Once the rebar is done and some pieces of concrete are poured near the abutments they can schedule the concrete pour for the bridge deck. The Bridge deck will vary from 9 inches thick all the way up to 14 inches thick but the majority of it will be 10 inches thick. A total of 450 cubic yards of concrete will be poured for the bridge deck.

The engineers designed the girders with enough strength that if later on they want to refinish the bridge without removing any of the old decking they can pour another road surface on top of the old deck and the bridge can take the extra weight. I will have to confirm but I believe up to another 4 inches can be added across the whole bridge.

Concurrently with the iron work across the deck of the bridge the crew is building forms at each abutment for special concrete blocks that will connect in between each of the girders and serve to add sheer strength to the bridge. This concrete will prevent the bridge from changing from a rectangle to a trapezoid (as one of the crew members explained it to me). This concrete will be approximately 6 feet thick and go from the bottom of the girders to the top. It will not attach to the abutment in any way. The bridge will remain “floating” on its cushion of rubber.

These sheer walls will be the next concrete to be poured and must be completed before the bridge deck can be poured.

They are using an interesting technique if I remember correctly called compression sand forms where small wood boxes were built (shown in photo #3) and sand was compressed into them then the wood forms were built on top of these wood boxes full of compressed sand. Once the concrete is poured, and cured, and the forms are ready to be removed instead of fighting them all they have to do is clip the wire holding the wood boxes together and the sand inside just falls away leaving nothing holding the wood forms up. Then they just pull the wood forms out easily.

I could see looking down at the abutment that the polyurethane foam was installed on the abutment. It looked to be approximately 4 inches thick and it had a thin masonite board covering it in between it and the bridge. This foam if you recall makes up the expansion joint for the bridge to be able to expand and move in varying temperatures.

In photo number 4 you can see the structure of the bridge from inside in between the girders. The wood forms that will hold up the concrete and the red metal brackets that hold up the forms will all be taken out once the concrete is poured and cured. The metal cross beams will remain.

Underneath the bridge I can see many pen marks and notations everywhere. There are supervising engineers constantly inspecting the work looking for anything that isn’t quite right and marking it for further examination.

When I look at the plates holding the massive girders together I can see a seemingly random selection of bolts that are circled with pen. These are the bolts that were tested to ensure the proper tightness was achieved. Similar to how they test a random selection of bolts from each lot to make sure they meet manufacturing spec.

In the last photo you can see the bolts on the cross braces are not actually all the way tight yet. This is because the girders need to be able to move relative to each other. As the weight from the concrete bears on them they move and shift and if they are tightly fixed to each other this could throw the bridge off balance. Instead they leave the bolts on the cross braces only partially tightened for now then once the concrete is poured they go back and tighten the bolts up to spec.

You can see a mark on the bolt end and then two more marks on the cross brace. This tells them where the bolt started rotationally and where it needs to end up to be considered tight.

As I suspected concrete trucks will be coming soon. In the next few days they will pour the concrete for the sheer walls at the north and south abutments then towards the end of this month it will be time to pour the concrete for the bridge deck.

I can’t wait to see a solid surface on this bridge! It is coming together.

I went back recently and looked at some of my past posts. It was really interesting to kind of relive the construction process.

Cheers Everyone. More updates to come.

Caltrans Central Coast (District 5)

IMG_3196

IMG_3198IMG_3199

IMG_3200

25th Annual Jade Festival Postponed

Once again the BIg Sur Jade Festival will need to postpone its date of Oct. 6-8, 2017. Yesterday’s statement by Cal Trans Public Information Officer, Susana Cruz put the opening of the Pfeiffer Canyon Bridge as the middle of October. Since our festival is the first weekend of October we will not have that access which is required for our permit to operate.

We haven’t made a new date, although we’ll be looking at May again. If we choose May, we won’t have the southern access open through Mud Creek and that creates challenges for the porta potties to be delivered as well as many of our volunteers and musicians.

If we choose the following October we expect that the south access of Mud Creek will be open and we’ll be back to a fully open highway.
,
Mother Nature has her way and anything can happen, as we are well aware of, and we must always defer to her whims but for now, those are our choices. We’ll be making that decision soon and let you know the outcome.

If you have a preference, please let me know.

Regretfully,
Lisa Gering

Fire East of Soledad

2:30 pm – KION reports:  SOLEDAD, Calif. – Multiple fires have been sparked in South Monterey County.

According to Soledad Fire officials, a two acre fire was likely started by lightning strikes just after 2p.m. Monday.

Currently, they are fighting the blaze by air and ground.

There are reports of another fire also sparked by lightning in King City.

Strong thunderstorms made their way through Gonzales and towards Salinas just after 2 p.m. Lightning and gusty winds over 40 mph and small hail are possible as the storm rolls through.

2:15 pm – I can see it from the 101. It is behind the first ridge, maybe in the Pinnacles. I will look for further. Cal Fire is just off the 101 trying to figure out how best to get there.

Highway Closure Update, 9/11/17

Photos: Mud Creek (PM 8.9 attached) from Saturday, Sept. 9, Pfeiffer Canyon Bridge (PM 45.52 below) removing falsework (left) and placing the deck reinforcement (right) from last week.

PM 8.9 Mud Creek 9.9.17

image002

image008

HIGHWAY 1 UPDATE – Monday, Sept. 11:

Highway 1 in Monterey County continues to provide 35 total miles of Hwy. 1 to the public from south of Gorda (PM 10) to just south of Pfeiffer Canyon (PM 45.5), accessible only via Nacimiento-Fergusson Road. State Route 1 remains closed from north of Salmon (just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek event. State Route 1 south of Salmon Creek is accessible via State Route 1 in San Luis Obispo County, past Ragged Point to Salmon Creek.

REMINDER: Travelers CANNOT travel the entire length of Highway 1 but local businesses are open on both sides of the closure points at Pfeiffer Canyon and Salmon Creek.

Mud Creek (PM 8.9)
Mud Creek had a major slide on Saturday, May 20, 2017, losing 5 million cubic yards of material. Caltrans continues with its plan to realign the existing terrain. The projected timeline to safely open to public traffic is late-summer 2018 at an estimated cost of $40 million.

There is currently no public access through the Mud Creek area since this remains an active construction zone.

Paul’s Slide (PM 21.6)
Paul’s Slide is still active but the 24/7 one-way reversing traffic control with flaggers will be replaced by a traffic signal and temporary guardrail (k-rail) in the centerline. Installation began last Tuesday, Sept. 1 and work continues this week.

Pfeiffer Canyon Bridge [PCB] (PM 45.52)
The bridge girder lowering process is complete and the girders are in their final position. Placement of the deck reinforcement is taking place as well as disassembling the remainder of the temporary falsework and completion of deck forming. The completion and opening of the new bridge is scheduled in mid-October.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information on this project and for traffic updates on other Caltrans projects in Monterey County, residents can call the District 5 toll free number at 1-831-423-0396 or can visit our website at: http://www.dot.ca.gov/dist05/paffairs/release.htm#mon.

Susana Z. Cruz
Caltrans District 5
Public Information Officer
Portavoz de Relaciones Públicas
para Caltrans en el Distrito 5
805.549.3138
805.549.3326–fax
Follow us on Facebook
We welcome your feedback: https://www.surveymonkey.com/r/RNBZG55

Nacimiento Rd. May be temporarily blocked & possible wildfire east of Nacimiento campground?

From CHP website, just happened 5 miles up from Highway One:

Incident: 00192 Type: Trfc Collision-Unkn Inj Location: Nacimiento Fergusson Rd / Sr1 Loc Desc: 5 MI JEO 1 Lat/Lon: 35.988672 -121.494108
Detail Information
12:38 PM 4 [8] NOT WI VEH
12:38 PM 3 [3] 1125
12:37 PM 2 [2] GOLD OR BRO CAB/ CHROME TANKER
12:36 PM 1 [1] BIG RIG VS HILL
Unit Information
12:37 PM 2 Unit Assigned
12:37 PM 1 Unit Enroute

From WildCAD-LPF (coordinates put it east of Nacimiento Campground)

Type Location WebComment Resources IC Fuels Acres Lat/Lon
09/10/2017 12:44 LPF-2725
New Wildfire . . . . . . 36.0090, -121.4036

Sunday Photos, 9/10/17

On a very hot end-of-summer day: (photographer prefers to not be identified to avoid accidental identification of spot and person in photos)

IMG_20170902_164012

IMG_6509

IMG_20170708_160147

New Zealand’s Highway One Landslide

New Zealand and Big Sur share several things in common – the Pacific Ocean, Jade, Mountains that meet the Sea, and incomparable beauty. There is a fifth thing we share; problems with our Highway One coastal route. I thought a bit of perspective might be in order this Saturday, given our news (or lack thereof) of Mud Creek yesterday.

Just a note, the trip around to get from one side to the other on New Zealand’s Highway One is SEVEN and A HALF HOURS, so Big Sur, consider yourselves lucky.

New video footage released today (9/7/17) highlights the challenges the North Canterbury Transport Infrastructure Recovery (NCTIR) crews working at Ohau Point, north of Kaikoura, are facing daily as they construct a new highway around the base of the major landslide.

Ohau is one of the largest and most challenging landslides still to be cleared, stretching 630 metres around New Zealand’s famous Fur Seal Sanctuary. More than 100,000 cubic metres of material fell down during last November’s earthquake and a clearance and rebuild operation has been underway for most of this year to reconnect communities.

“While abseilers are still working to make safe the northern face of the slip, teams have spent the winter months constructing the foundations for a new seawall where a road and shared path will eventually sit,” says NZ Transport Agency Earthquake Recovery Manager Steve Mutton.

“Despite freezing cold conditions and sudden tidal changes, the crews have made great progress,” he says.

IMG_3171

The new footage also shows for the first time, the teams working to keep the seal colony safe by carefully moving pups and adult seals out of the construction site. Permits granted under the Marine Mammals Protection Act 1978 mean NCTIR team members can physically move the seals. Using helicopters and specially trained seal handlers, the seals are shifted out of harm’s way so machinery can continue making progress.

Seals in pools on an access road north of Kaikoura earlier this year
Seals in pools on an access road north of Kaikoura earlier this year

“Kaikoura’s natural environment is beautiful and special and we want to look after it. Every morning our crews move the seals to safety before the rest of our team starts work.”

Meanwhile, a major operation to install 6000 square metres of steel mesh is well underway on top of Ohau’s fragile northern face. Due for completion in September, the mesh will allow crews to safely clear the small mountain of material still waiting to be shifted underneath. It will also signal the start of construction of a new seawall and road on the northern side of the slip.

Seawall teams are currently working at Irongate, closer to Kaikoura, and Ohau to build 2.5 kilometres of seawalls. Each block weighs 5 tonnes and more than 7000 of them are needed.

“At Ohau, the old road will be used as a catch bench in case any rocks fall in the future. This means contractors will be able to clear the material without causing disruption to the road network.”

Situated in the middle of the northern coastal corridor, Ohau wasn’t easy to reach. Crews had to build access tracks around the other nine landslides from the northern and southern ends in order to reach Ohau in the middle.

Following a successful helicopter sluicing operation at Ohau Point, earthworks teams spent two months benching the landslide to make it safe enough for machinery to cart more than 8000 truck and trailer loads off the southern side of the point during a two month 24/7 operation.

“We are really proud of the work these crews are doing and the way people are working together to reconnect communities along the Kaikoura coast and ensure our wildlife are safe,” says Mr Mutton. “It is a unique environmental and construction challenge but we are now starting to see visible progress after months of preparation.”

Check our Facebook post (external link)today which has the video online. If you have a FB account, you can see videos of their progress on their page. https://www.facebook.com/nztasouthisland/

 

Mud Creek to open end of Summer 2018

Caltrans Announces Projected Timeline for Rebuilding Highway 1 at Mud Creek

BIG SUR, MONTEREY COUNTY – Caltrans is aiming to have Highway 1 at Mud Creek open to traffic by late summer, 2018 with an estimated price tag of $40 million. Earlier this summer, Caltrans announced a plan to build over the massive slide that covered Highway 1 earlier this year. The new roadway will traverse over the slide area, using a series of embankments, berms, rocks, netting, culverts and other stabilizing material.

“The landslide at Mud Creek is one of the largest in California’s history. We are working to safely rebuild the road in this complex and unpredictable area,” said Caltrans District 5 Director Tim Gubbins. “We understand how much this road closure has impacted the counties of San Luis Obispo and Monterey, and we appreciate everyone’s patience and support as we work to open the highway. Caltrans is committed to restoring this vital link to and from Big Sur as quickly and safely as possible.”

The timeline for rebuilding is dependent on this winter’s weather conditions. Caltrans will continue working closely with various state, local and federal resource agencies and the Big Sur community until the highway is reopened.

The landslide occurred May 20th and sent more than 5 million cubic yards of rock and dirt onto the roadway and into the ocean, making it the largest slide ever along the Big Sur coast.

–Photos below–

Aerial photo courtesy of John Madonna Construction from May 25, 2017

image003
Aerial photo courtesy of John Madonna Construction from Friday, Sept. 1, 2017

image005
Susana Z. Cruz nature-flower-blue-motif[1]
Caltrans District 5
Public Information Officer

Adler Ranch Acquisition Petition

The Adler Ranch has a crucial firebreak and is for sale. The US Forest Service proposes to buy it through the Western Rivers Conservancy. Experience shows that such public ownership of the Adler Ranch would likely result in the loss of that fire break and thus increase the threat of wildfires to our community.

*** HERE IS THE LINK FOR THE PETITION PAGE TO PREVENT THE ACQUISITION ***

http://PALO-PETITION.weebly.com

During the Basin Fire in 2008, the Adler Ranch was the location of 1.6 miles of firebreak that was used to stop it from burning through the Rocky Creek, Palo Colorado, and Garrapata watersheds.

ForKate

One of the scoring criteria is whether there is support for the acquisition in the local community and/or from local elected officials. The Western Rivers Conservancy is working to collect statements of support for the acquisition.

The Coast Property Owners Association, Fire Safe Council For Monterey County, and others are opposed to the acquisition. They are working to explain why the acquisition would not meet the criteria, to oppose the acquisition. Your signature on the petition will help that effort by showing the acquisition does not have local support.

Mike Caplin built a one page website you can use to sign a petition that will be given to Congressman Panetta, the Forest Service, Senators Feinstein and Harris, and others.

For those of you who may want more information the petition has a lot of information in its “Whereas” section, including links to documents and video clips to back up what it says.

At the top of the web page is a link to skip to the bottom so you can go straight to signing the petition if you already feel well informed.

If you agree, please sign the petition and pass it along to others who share your concerns. Time is of the essence, so please take a few minutes to review the petition and sign it today.

Bridge Update by Kyle Evans

The bridge has landed. As of approximately 9:30am this morning the bridge made its final descent onto the abutments.

The bridge is now sitting with a rubber pad and steel plate under each girder at both ends of the bridge.

What a momentous occasion to witness. That last 5 inches felt like a very long distance after the marathon of work that went into getting this 900 ton bridge lowered approximately 17 feet into place.

The second image is a detail shot showing the rubber pad and the steel plate under each girder. The bridge is designed to be a floating bridge. It is allowed to flex and move and the rubber pad facilitates this movement and protects the abutment. The steel plate protects the rubber pad and is shaped like a wedge to accommodate the curvature of each girder and allow them to sit flat.

A huge congratulations to the crew for all their hard work. This is a big milestone today.

The next step is to remove all of the temporary work on the bridge and abutments. Forms will be put in to be able to pour the last bits of the abutment that had to wait until the bridge was in place before they could be completed.

On top of the bridge the wood forms continue to be assembled. Once the wood forms are completed on the surface of the bridge the steel workers will come in to build the rebar cages for the concrete.

More to come.

Caltrans Central Coast (District 5)

IMG_3167IMG_3168