Rocky Creek Viaduct update with photos

Below is an update I received today from one of the inspectors at the Rocky Creek jobsite:

—————————————————————————————————————————————————————
“CIDH piles for bents 3, 4, 5 an 6 are complete. Contractor is currently working at bent 2 pile. The average production rate for the piles is still approximately 1 pile per week. However, bent 2 pile may take longer as drilling can only be performed during the night under full closure due to space constrains. Placement of the piles is on schedule.”
————————————————————————————————————————————————————–

I have attached a photo below that illustrates this information:

(See attached file: Updated drilling locations.JPG)

Also, I’m going to be on a Monterey TV program tomorrow discussing the Rocky Creek project as well as the Pitkins Rock Shed project. Not sure if you can get this program where you are but I thought I’d mention it. Below is a link to more information.

http://montereytelevision.com/YourTown.htm

Have a good day!

Ken

20121127-190712.jpg

Also, here is a photo of a bridge showing the part labeled “the bent.”

20121128-110830.jpg

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.