** UPDATE #22 **
HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT CONTINUES WITH DAYTIME ROADWORK AND INTERMITTENT OVERNIGHT CLOSURES
Daytime roadwork on Highway 1 continues next week from 7 am to 5 pm Monday, March 18 through Friday, March 22.
Overnight closures next week are as follows:
· Sunday, March 17 through Thursday, March 21—9 pm to 7am—full closure each night; details are as follows:
o Sunday, March 17 through Monday, 18 (7 am)—full closure will be the usual project limits;
o Monday, March 18 through Thursday, March 21 (Friday 7am)—EXTENDED full closure will begin just north of Rocky Point Restaurant to the usual project limits;
Bridge work being done on Sunday night is girder prep work. Monday through Thursday overnight work is girder installation. The 90-ft long girder delivery trucks need to back up to install girders—therefore necessitating the extended full closure from just north of Rocky Point Restaurant to the project limits.
NOTE: Residents will be allowed to get through the 2-mile section between Rocky Point Restaurant and the project limits during the overnight full closures from Monday through Thursday night (Friday am)
Highway 1 at Rocky Creek has one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes at a time during daytime roadwork. Full overnight closures will be scheduled five nights a week Sundays through Thursdays, unless otherwise indicated. No overnight closures will occur on Friday/ Saturday nights.
The project to construct a permanent viaduct about 15 miles south of Carmel near the Rocky Creek Bridge began on Sept. 4. Completion is scheduled by Labor Day, weather permitting. Daily roadwork schedules are subject to change due to weather conditions and other factors so stay tuned for regular updates.