New Road Work in Big Sur next week, 7/7-7/13

I see no reason to publish the entire TAMC report each week, so here is the new information specific to Big Sur.

Highway 1: Hot Springs Creek Bridge – Burns Creek Bridge, Big Sur: July 9   
One lane closure will occur on northbound and southbound Highway 1 between Hot Spring Creek Bridge and Burns Creek Bridge in Big Sur for a crack seal operation from 8 a.m. to 3 p.m.

Highway 1: Burns Creek Bridge – Anderson Canyon Bridge, Big Sur: July 11   
One lane closure will occur on northbound and southbound Highway 1 between Burns Creek Bridge and Anderson Canyon Bridge for utility work from 7 a.m. to 3:30 p.m.

Highway 1: Ventana Entrance – Nepenthe North Entrance, Big Sur: July 9   
One lane closure will occur on northbound and southbound Highway 1 between the entrance to Ventana  and the north entrance of Nepenthe for a crack seal operation from 8:15 a.m. to 1:30 p.m.

Highway 1: Pfeiffer Canyon  Bridge – Ventana Entrance, Big Sur: July 10July 12   
One lane closure will occur on northbound and southbound Highway 1 between Pfeiffer Canyon Bridge and Ventana entrance for survey work from 8 a.m. to 3:30 p.m.