Road Closure Update, 3/20/17

SR-1 Full Closure—Ragged Pt (SLO PM 72.87) to the Multi-Agency Facility “MAF”(MON PM 46.35). Please note changes since last Friday below:

· Nacimiento-Fergusson Road is now open to the public.
· Public access on Highway 1, using Nacimiento-Fergusson, will be to Gorda (PM 10) to the south, and to Limekiln State Park (PM 20) to the north.
· There will be a complete closure at Paul’s Slide (PM 21.6). Residents will have limited access (mornings from 5:30am – 6:00am and evenings from 7:00pm – 7:30pm). These daily windows will not allow for deliveries.
· Friday deliveries: Residents and deliveries will be allowed through at Paul’s Slide and Mud Creek once per week on Fridays between 5:30am – 9:00am, and 5:00pm – 7:30pm. Delivery vehicles are limited to 30 feet in length and up to 50,000 pounds.
· Residents will have access between Ragged Point and Limekiln State Park and from north of Paul’s Slide to just south of Pfeiffer Canyon Bridge between 5:30 am and 7:30 pm. Starting tonight, Monday, March 20th, four gates will close the roadway overnight at the following locations: 1) south end of Mud Creek (PM 8.8); 2) north end of Mud Creek (PM 8.9); 3) North end of Limekiln Creek Bridge (PM 21.07) and 4) north end of Hermitage wall (PM 22.42).
o Emergency services will have overnight access to the locked gates.

Mud Creek (PM 8.9):
· The roadway continues to deteriorate as slide activity continues daily. Further updates about the ability to pass through this section will be provided as the slide stabilizes.
· For now, resident access will continue to be allowed daily between 5:30 am and 7:30 pm.

Paul’s Slide (PM 21.6):
· Starting Wednesday, March 22nd , there will be limited access due to major excavation above the roadway; access is limited to 5:30am – 6:00am and 7:00pm – 7:30pm. This will be for a minimum of four to six weeks and we will continually evaluate for opportunities to improve local resident access.
· For the Friday opportunities to resupply, access is limited to vehicles weighing 50,000 lbs., with a maximum vehicle length of 30 feet.
· Work will performed 24/7 as conditions allow, and updates will continue to be provided.

IMPORTANT NOTE – CALTRANS PFEIFFER CYN. BRIDGE (PM 45.5):
· Demolition of the bridge is nearly complete. Please stay clear of the area for your own safety and to allow the construction team to work on re-building this vital part of the road.

All business north of the Pfeiffer Canyon Bridge closure are open to the public.

ADDITIONAL NOTES:
· Due to the nature of the construction activities, access will be subject to change on a regular basis.

· Another update regarding the Highway 1 Big Sur Coast will be provided mid-day on Tuesday, March 21 or sooner if conditions change.

· NOTE: For information on emergency services only (not Caltrans inquiries) for the Big Sur Coast, you may contact Gerry Malais, Mon. Co. OES via email at: malaisg@co.monterey.ca.us or Maia Carroll, Mon. Co. OES PIO at carrollm@co.monterey.ca.us or via phone at (831) 796-3092.

NOTE: TODAY TWO PEOPLE USED NACIMIENTO TO MAKE THEIR WAY ALL THE WAY UP TO POST RANCH. THIS WAS REPORTED TO CAL TRANS WHO INDICATED THEY WILL BE LOOKING TO PREVENT THIS. IT WAS REPORTED TO ME AND I WAS ABLE TO COPY IT AND SEND IT ON TO CAL TRANS. PLEASE CONTINUE TO SEND ME THIS TYPE OF INFORMATION SO I CAN FORWARD IT ON TO THE POWERS THAT BE.

To all our Big Sur visitors, particularly bicyclists …

I have been getting a lot of requests lately from bicyclists and others about the use of the trail that is being constructed partially by locals for locals through a closed area, and I would offer this observation: the community does not think this (the use of the trail by bicyclists or others) is a good idea. It is narrow and steep, and full of steps. We are trying to heal. The path is an emergency measure for those who live here who are trying to survive – separation from loves ones; separation from work and home; and separation from children and their schools. It is our way of surviving, not a way to welcome guests. We would ask the bicycling community and others to honor and respect the healing we are trying to obtain in a difficult situation and time. I know you would love to experience the coast without all the cars, so would we. However, it is not just the bridge, it is the other two problems – Paul’s Slide and Mud Creek, one of which will be closed to visitors all of April and probably May as well. So the trail will not get you down the coast. There are other closures preventing a through passageway.

We want visitors, our community makes most of our living off of visitors, but we want them when it is safe for all. Please, we will welcome you when the road is open, but not when it is not open or safe. If you love Big Sur, honor her. She is saying she has had enough for now. Let her rest and recover. Let us rest and recover, we spent all summer fighting fire; we have been burned out of our homes; and winter has brought us floods that have ruined our roads. We are fragile, as a people and as a land. When the road is open, completely, or only just from the south or just from the north, we will welcome you. Right now, it is only open on the north from Carmel to the MAF – Big Sur Ranger Station, and not at all on the south. Bring your tourist dollars to the area and businesses that are open, but … Please. Honor Big Sur and the people who live here and the land and the people’s need to heal. If you love Big Sur, you will listen to what she is saying … give her and us time. Please.