FOR IMMEDIATE RELEASE
*Update #1*
CALTRANS ANNOUNCES NEXT CONVOY TO PFEIFFER CANYON BRIDGE

MONTEREY COUNTY – Caltrans will continue the process of delivering construction equipment and materials to the site of the demolished Pfeiffer Canyon Bridge on State Route 1 via Nacimiento-Fergusson Road from US Highway 101 on Thursday, May 18.

This single convoy will be escorted by the California Highway Patrol and will include full closures of Nacimiento-Fergusson Road at 8 am. Motorists traveling westbound should do so before the convoy begins. Motorists wishing to travel eastbound towards US Highway 101 after 8 am will be held at State Route 1 until the convoy passes. This is the only convoy scheduled and will take about four hours to complete the round-trip, allowing for both access times at Paul’s Slide to take place as scheduled.

This convoy will include six 10-wheeler trucks full of fine aggregate (sand), which will be used to construct concrete abutments for the new bridge. An update on future convoys will be sent out when information has been confirmed.

The steel girders for the new bridge are currently being fabricated at a plant in Vallejo, CA.
The girders will then be moved to a plant near Stockton for painting before they are shipped to the Pfeiffer Canyon site. This $24 million project is expected to allow public access in mid to late September.

Caltrans reminds motorists to move over and slow down when driving through highway
work zones.

For more information on this project and for traffic updates on other Caltrans projects in
Monterey County, residents can call the District 5 toll free number at 1-831-423-0396 or can
visit our website at: http://www.dot.ca.gov/dist05/paffairs/release.htm#mon

Mud Creek photos, 5/17/17

These were taken Monday, 5/15/17 by Rock Knocker. Several of them show the north side of the slide Cal Trans sent yesterday, which was taken on the south side. WARNING: These are depressing. It was very active and he got photos of the activity, but I didn’t get them transferred yet. This slide show is 22 photos and I have 64.

This slideshow requires JavaScript.

Highway One remains closed until further notice, 5/16/17

1-2) Photos of Mud Creek (PM 8.9) attached.

PM 8.9 Mud Creek 5.15.17

PM 8.9 Mud Creek-1 5.15.17

Photos of Pfeiffer Canyon Bridge Construction (below)—courtesy of Kyle Evans for Caltrans.

* AN UPDATED RELEASE ON NACIMIENTO-FERGUSSON CLOSURES WILL BE ISSUED TOMORROW, WEDNESDAY, MAY 15 WITH THURSDAY’S
CLOSURES)*

THE INFORMATION BELOW IS FOR LOCAL RESIDENTS AND DELIVERY VEHICLES ONLY

************************************************************************************************
· Mud Creek (PM 8.9) –NO ACCESS UNTIL FURTHER NOTICE. No ETO for Mud Creek at this time.
·
· Mud Creek has three major issues: 1) a partial lane missing; 2) the slope/roadway is at an angle and 3) significant slide material is still coming down. There is the possibility of retaining walls or a side hill viaduct as a viable solution for Mud Creek, but first we need to drill, and to do so, we need the slide to cease movement and the water to stop flowing. Vehicles and local residents will need to use Nacimiento-Fergusson to exit south or clear the access times at Paul’s Slide.
·
Paul’s Slide (PM 21.6)—ACCESS FOR LOCAL RESIDENTS AND DELIVERY VEHICLES
ONLY.
No Change. Work on the slope continues. The targeted “public access” date of mid-June
shows medium probability with recent activity, public opening date could be pushed further
out.

· 12:00PM Monday / Wednesday / Friday– A single caravan south and a single caravan
north, you must be in line by noon! There may be up to 45 minute delay to clear the road
before the opening.

· Delivery vehicles (Restriction is 30 feet maximum length and 50,000 lbs. maximum weight) can now use all access windows 7 days a week.

· Access times for the morning and evening are still the same except for Friday:

5:30AM to 6:00AM and 7:00PM to 7:30PM – Sat.-Thurs.

· Friday’s hours will be shortened to:

5:30AM – 8:00AM and 6:00PM to 7:30PM

· The noon opening will be for PAUL’S SLIDE ONLY, (NOT MUD CREEK); you will need to use Nacimiento-Fergusson Road to exit the coast.

Pfeiffer Canyon Bridge [PCB] (PM 45.52)
The foundation pile for the abutment and wing walls was completed last week (north end) and the drilling contractor is currently mobilizing the south end to begin the foundation work there. The contractor has begun demolition of the original abutment on the north side and will be focusing on excavation, forming, placing rebar and pouring the new abutment #2 on the north side over the next few weeks.

Progress continues to take place but being that Mud Creek is closed until further notice, we
need to bring 10 loads of material: gravel, sand, equipment and other items via convoys
through Nacimiento—Fergusson with CHP escorts—thus far scheduled for today and
Thursday of this week. Current public access date remains: Mid-to-late September.

Slide Removal within PCB Closure (PM 45.84)
Slide removal operations just north of the Pfeiffer Canyon Bridge project, which we are calling the “trailer
slide” will began yesterday, Monday, May 15. Temporary guardrail (K-rail) was placed yesterday and there
will be STOP sign controls in place 24/7 at PM 45.84 just north of Sycamore Canyon Road. This is within
the closure for the bridge project and will only affect residents of Pfeiffer Ridge Road and Sycamore Canyon
Road. Flaggers will control traffic during work hours. There may be some delay as trucks are loaded out.

Another update will be provided by mid-day Friday, May 19.

Photos of Pfeiffer Canyon Bridge construction below.

image002

North Side Abutment area. The piles have been poured and excavators and loaders are digging down preparing the area for the forms for the wing walls and the abutment.

image003

Left side a rebar cage is lowered into the ground for one of the piles that will form the foundation for the abutment. Right foreground. The drill rig clears out dirt built up on the drill while drilling the hole for the west wing wall.

image004

The crane (right side) is lowering a rebar cage into the ground that will become the foundation pile for the north
abutment. Another rebar cage is pictured on the ground in the foreground waiting to be lowered in. The drill rig can be
seen beyond the crane in the background drilling the hole for the foundation pile for the west wing wall.

Susana Z. Cruz
Caltrans District 5
Public Information Officer
Portavoz de Relaciones Públicas
para Caltrans en el Distrito 5
805.549.3138
805.549.3326–fax
Follow us on Facebook
We welcome your feedback: https://www.surveymonkey.com/r/RNBZG55

Paul’s Slide has been active at night

From someone who went through at the 5 am opening, she stated they had to wait 1/2 an hour for it to be opened up due to new slide activity. She sent these photos of that trip:

IMG_2455IMG_2456

2nd Nacimiento Convoy announced For Thurs. 5/18/17

Attached are the releases for the convoy this Thursday 5/18 as well as the one scheduled for tomorrow 5/16:

Today’s Date: Monday, May 15, 2017
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa Cruz Counties
Contact: Susana Z Cruz (bilingual) or Jim Shivers
Phone: (805) 549-3138 or 549-3237
FOR IMMEDIATE RELEASE

CALTRANS ANNOUNCES NEXT CONVOY TO PFEIFFER CANYON BRIDGE

MONTEREY COUNTY – Caltrans will continue the process of delivering construction equipment and materials to the site of the demolished Pfeiffer Canyon Bridge on State Route 1 via Nacimiento-Fergusson Road from US Highway 101 on Thursday, May 18.

These convoys will be escorted by the California Highway Patrol and will include full closures of Nacimiento-Fergusson Road beginning at 8 am. Motorists wishing to travel westbound should do so before the convoy begins. Motorists wishing to travel eastbound towards US Highway 101 will be held at State Route 1 until the convoy passes.

This convoy will include two concrete boom pumps, two mobile mixers and a Vactor truck. This equipment will be used to construct concrete abutments for the new bridge.

The steel girders for the new bridge are currently being fabricated at a plant in Vallejo, CA. The girders will then be moved to a plant near Stockton for painting before they are shipped to the Pfeiffer Canyon site. This $24 million project is expected to be open to the public in mid to late September.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information on this project and for traffic updates on other Caltrans projects in Monterey County, residents can call the District 5 toll free number
at 1-831-423-0396 or can visit our website at: http://www.dot.ca.gov/dist05/paffairs/release.htm#mon

Jim Shivers
Caltrans District 5
Public Information Office

Community Meeting – Southside

BIG SUR COMMUNITY MEETING
WHEN: TUESDAY MAY 16
TIME: 5:30-7PM
PLACE: BIG SUR BAKERY PATIO
WHAT: BE PART OF THE SOLUTIONS
WHY: BECAUSE WE CARE
WHO: SOUTHSIDE RESIDENTS
WHAT ELSE? Come express your ideas and solutions. There will be an opportunity for each person to voice one concern and a solution. (Depending upon the size of the group we may be able to hear your second and third concern.) One goal of this meeting is to hear from the Southside locals what their main concerns are and to come up with a list of potential solutions. Meeting will be bilingual if requested.
The results of this meeting will be taken to the Unified Command.

contact person: carissa@chappellet.com
Serving: Juice/Fresh Veggies/Dips/ Chips/ Popcorn
GRAN SUR COMMUNITY reunión
Al: Martes 16 de mayo
Tiempo : 5:30-19:00
Lugar : Gran SUR panadería PATIO
Lo que : Ser parte de las soluciones
Por qué : Porque nos importa
Que : Los residentes de la zona sur
Qué otra cosa ? Venga a expresar sus ideas y soluciones. Allí será una oportunidad para cada persona expresar una preocupación y una solución. (Dependiendo del tamaño del grupo podamos escuchar su segunda y tercera preocupación.) Uno de los objetivos de esta reunión es escuchar a los lugareños de la zona sur Cuáles son sus principales preocupaciones y con una lista de posibles soluciones. Reunión será bilingüe si así lo solicita. Los resultados de esta reunión se tomarán el comando unificado de.

persona de contacto: carissa@chappellet.com
Porción: Jugo/ dulce verduras/Dips/Chips / palomitas de maíz

Some of the Issues:
Trail Usage/ Trail Parking/ Helicopters/ Shuttle Busses/
Southside turn-around/Softball league…..

Mud Creek Evaluation & Photos

If you were at the BSMAAC meeting, you heard me speak briefly to this, giving everyone my opinion that we are in it for the long haul, as in it is possible it may take a year. I base this opinion on several other decades-long residents’s opinions and observation. We also have seen the top of the slide, from a position up Willow Creek on San Martin Top. We have been watching it for months, and the whole mountain is giving way. I will try to make time to post some of the earlier photos and latest photos of this phenomena. Today, Cal Trans sent me Sara’s (she was at the meeting) evaluation of the situation. This will not be an easy fix. It is complex. It follows:

“The Mud Creek area is a volatile location with the conditions and expressions of landslide movement changing on a regular basis. We have been actively managing and maintaining a single lane through this location for 4 months. The conditions at this site have actually increased in activity over the last few weeks as is evident from the debris that is continuing to come down these slopes. The landmass is clearly moving in different ways at different times along this 0.4 miles stretch of the highway. The slopes above the roadway have been saturated and are slumping due to the extensive springs and seeps that have developed this winter. Fine grained material is being eroded and leaving large blocks of rock (greater than 10 feet in diameter) exposed which eventually become undermined and come hurtling down the mountain. We have worked below this active slope to remove the debris which lands on the roadbed and have been trying to maintain the existing roadbed width while it has been too unsafe to put equipment up on the slide.

Even though the rains have essentially stopped, activity on this slope has increased and more debris and large blocks of rock are moving down the mountain. With the increase in slope failure activity we have been forced to reduce the exposure of the public and the workers to these conditions. With all the erosion, there is currently overhanging debris and towers of rock exposed high above the roadway. It is actually not uncommon for slope activity to increase well into May. Large catastrophic landslides are definitely known to occur in the month of May well after the rain has stopped. For this reason we are not able to work the slope as we would like. Losing this access point on the coast has very large impacts to all stakeholders. We are currently in the process of setting up a large scale monitoring system that will help determine slope movement as well as working with USGS to review the movement that is occurring hundreds of feet above the roadway. With an understanding of whether the slope movement is slowing, dilating, increasing, or bulging, we will be in a better place to determine the safety at the site for people working on the slopes as well as people traveling along the roadbed.

Long-term solutions are being developed at this site but we have not been able to mobilize the drill rigs for the geotechnical investigation due the exposure to rock fall to the workers and large-scale landslide movement. Mud Creek is a series of landslides adjacent to each other with differing slide planes and rates of motion. As such, this complex of slides is the largest and most difficult situation that Caltrans has had to manage along the Big Sur Coast. Caltrans will continue to keep the public informed as solutions are explored both internally and with our partners at the USGS.”

IMG_2446

IMG_2447

IMG_2448

One can see that the existing roadbed is fast disappearing. Trust me, Cal Trans is being pressured on all sides to get this open, and they are doing everything in their power to do so. It is not possible at the moment. The damage has been done and is only getting worse. Mistakes have been made, but blame doesn’t solve the problem. This is where we are, and this is where we must start to find solutions which will work. It will take significant further study, when it is safe. Not much can be done while the water continues to flow out of the mountain and it continues to fall.

This has been an historical summer (Soberanes Fire) and an unprecedented winter – one for the history books. It is a story our grandchildren will know and tell. We will sur-vive and we will become stronger as a community. We already have. We have witnessed amazing acts of kindness and community acting together in creative problem-solving ways. There are so many heroes it is hard to list them all. It is not over, but I have faith in who were are and what we can do. I am proud of us.

 

Convoys over Nacimiento, Tuesday, 5/16/17

PFEIFFER CANYON BRIDGE CONSTRUCTION MATERIALS ARRIVE NEXT WEEK

MONTEREY COUNTY – Caltrans will begin the process of delivering construction equipment and materials to the site of the demolished Pfeiffer Canyon Bridge on State Route 1 via Nacimiento-Fergusson Road from US Highway 101 on Tuesday, May 16.

These convoys will be escorted by the California Highway Patrol and will include intermittent full closures of Nacimiento-Fergusson Road from 8 am until 7 pm. Motorists wishing to travel east/west in the morning must do so before the first convoy begins.

Motorists will encounter delays during the movement of these four convoys westbound from 8 am to 10 am and 2 pm to 4 pm and eastbound from 11 am to 1 pm and from 5 pm to 7 pm. Motorists who wish to travel on Nacimiento-Fergusson road should be in vehicles not exceeding 30 feet in length and a weight of 15 tons.

These convoys will include about 50% of the rock and sand necessary to create concrete abutments for the new bridge. Future convoys will transport additional rock and sand, two mobile batch plants, two concrete boom pump trucks, vacuum trucks and rebar cages. Dates for these convoys will be announced at a later date.

The steel girders for the new bridge are currently being fabricated at a plant in Vallejo, CA. This $24 million project is expected to be open to the public in mid-September.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information on this project and for traffic updates on other Caltrans projects in Monterey County, residents can call the District 5 toll free number at 1-831-423-0396 or can visit our website at: http://www.dot.ca.gov/dist05/paffairs/release.htm#mon