FOR IMMEDIATE RELEASE
HIGHWAY 1 CLEANUP AND ASSESSMENT AT RAT CREEK CONTINUE; SOUTHERN CLOSURE SCHEDULED TO SHORTEN
Work continues unplugging numerous culverts both north and south of Rat Creek which were overwhelmed by debris flow from the recent rainstorm. Significantly, all the culverts have been located and their inlets exposed. Additional debris removal from the inlet areas and removal of mud and debris from inside the pipes continues.
Caltrans maintenance forces continue work in the open sections of the highway clearing ditches and debris. Crews continue to work in support of emergency contractors inside the closed sections of highway with guardrail repairs and restoring drainage facilities. Crews will continue to work extended shifts through the holiday weekend.
Southern Closure Scheduled to Move North
The closure of Highway 1 south of Rat Creek is currently in place just north of Pacific Valley at PM 16. Given current progress on debris removal and road repairs, it is anticipated that this southern closure will move north on Monday Feb. 22, and relocate to the Big Creek Vista Point at PM 27.3 where a turnaround is being constructed.
Northern Closure in Place
A turnaround has been put into service two miles north of Rat Creek, just north of the Lime Creek Bridge at PM 32.1. This turnaround will serve as the landmark limit for public travel south on Highway 1 while repairs are being made at Rat Creek.
In upcoming weeks, the turnaround will be improved with permanent surfacing and enhanced striping. Work to restore impacted drainage systems on Highway 1 north of Lime Creek will continue using standard traffic control as necessary.
Assessment Continues at Rat Creek
Crews continue working at Rat Creek seven days a week as part of the ongoing assessment phase. Geotechnical and engineering crews continue to gather data and inspect areas in proximity of the washout and the surrounding canyon. To date, no design alternative has been selected. Given the complexity of the repair there is at present no timeline for when this decision will be made.
Excavators have mobilized on site to remove woody debris and mud from the canyon. Such work is required no matter the design alternative selected.
Caltrans reminds motorists to move over and slow down when
driving through highway work zones.

Excavators Clearing Debris and Mud at Rat Creek 02.11.21
###
Kevin Drabinski
Public Information Officer
Caltrans District 5










Our biggest constraint with the vaccine distribution continues to be the amount of doses we are allocated each week. Monterey County’s capacity to administer vaccines is 17,100 doses per week, but we currently only receive a supply of 2,000-4,000 doses per week. Monterey County has secured sites that will be used for large scale vaccination clinics for when we begin to get greater supplies. Until we receive more vaccine allocations, we will continue to focus on the most at-risk residents in Monterey County. As you may know, the reason we do not receive the number of vaccines neighboring counties do is because we do not have any Multi-County Entities (MCEs) in our county. MCEs are those health care facilities present in multiple counties such as Kaiser, Sutter and Dignity. They are allocated an additional amount of vaccine before the rest of us get ours. Options for Veterans 