Events in MoCo – a way to get involved

Want to be heard on the holding of special events on Highway One? Like the Dream Drive promoted by California, Central Coast and MoCo tourist agencies? Consider coming to as many of these meetings as you can. Once a month, in Salinas. Or let’s set up a rotating crew of Big Sur residents and workers to make sure our voice is hear.

Monterey County Special Events Task Force
Post Car Week Discussion
The August Special Events Task Force Meeting will be held on August 30thin the Cayenne Room. This will allow for post Car Week discussion. The agenda is forthcoming. The Resource Management Agency (RMA) of Monterey County cordially invites you to participate in our Special Events Task Force.

WHAT: Special Event Task Force, a collaborative effort to promote hassle-free special event permitting to ensure safe and successful events in Monterey County.

WHO: Special event organizers and stakeholders (e.g. hospitality industry, tent rental companies, event support companies, etc), Monterey County regulatory agencies, interested members of the public.

WHY: Event organizers will gain valuable insights and feedback on the ins and outs of special event permitting in Monterey County. County regulators will get the opportunity to provide transparency on their processes to organizers and the public. Members of the public will be able to voice their comments, interests and concerns regarding event planning in their community.

WHEN: Every fourth Thursday once a Month from 9:00-10:30 am

WHERE: The Thyme Room, Monterey County Government Center, 1441 Schilling Place, 2nd Floor, Salinas 93901

Big Sur Information

Header photo by bigsurkate

****************************************************************************

AS OF 2/16/26 — HIGHWAY ONE IS CLOSED FROM RAGGED POINT TO 1 MILE SOUTH OF DEETJEN’S UNTIL FURTHER NOTICE DUE TO MULTIPLE ROCK AND MUD SLIDES.

*****************************************************************************************

Links for phone users who can’t see the links to the right without scrolling through two years of posts. I’ll start with just a few, but if you have others you wish to see here, let me know.

Big Sur Maps (3) with slide names, locations, etc.: https://bigsurkate.blog/big-sur-interactive-highway-maps-with-slide-names-mile-markers/

Caltrans Interactive Map: https://quickmap.dot.ca.gov/

CHP dispatch: https://cad.chp.ca.gov/Traffic.aspx

 

******************************************************************************

Interactive Highway Map with Mile Markers and slide names is to the right, under “Pages” first one *Big Sur Interactive Maps... if the following link doesn’t work. *Big Sur Interactive Slide Maps will answer any questions you may have about where something is in relation to something else.

MY DIRECT EMAIL IS: kwnovoa(AT)mac(dot)com

 

Highway to open tomorrow, Weds. 7/18 at 10 am

CALTRANS
Today’s Date: Tuesday, July 17, 2018 at 1:30 pm
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa Cruz Counties                                                  
Contact:  Susana Z. Cruz (bilingual) or Colin Jones
FOR IMMEDIATE RELEASE                     
###TRAFFIC ADVISORY###
STATE ROUTE 1/MUD CREEK WILL OPEN TOMORROW, WEDNESDAY, JULY 18 BY 10 AM
 
MONTEREY COUNTY– The contractor made great progress in the last several days so final striping and inspection by our crews is underway. As a result, Highway 1 at Mud Creek will RE-OPEN by 10 am tomorrow, Wednesday, July 18, nearly 14 months after the massive landslide and emergency repair project.
 
Electronic Message Signs will be changed once the highway is open, also Headquarters Communications and QuickMap will be updated.
 
Our official ribbon-cutting/community celebration remains set for Friday, July 20 at 11 am at the Ragged Point Inn.
 
This $54 million repair included the reconstruction of ¼-mile of new roadway alignment built on the slide material and a compacted embankment at the south and north ends. The new highway extends out towards the ocean upwards of 250 from the original highway. The roadway is 150 to 260 feet above sea level and buttressed with a series of embankments, berms, rocks, netting, culverts and other stabilizing material.
 
IMPORTANT NOTE: All roadwork is still not complete at Mud Creek. Travelers may encounter one-way traffic control at times when a lane closure is needed, mostly on weekdays. Also, due to the cuts and work on the embankment and roadway at Mud Creek, it will take about two winters for the new slopes to fully stabilize.
 
The public may learn more about this and other projects by visiting the Caltrans District 5 News Release page at: http://dot.ca.gov/dist05/paffairs/release.htm.
 
 
Aerial photo of Mud Creek from today courtesy of John Madonna.
0C3565E6-31D7-4290-B5D7-8908D679A413

Highway Closure Update, 6/4/18

Basically, nothing has changed. Mud Creek opening still anticipated for mid September, Paul’s Slide continues with one light, traffic signal controlled traffic. Here are this week’s photos:

Two photos of Mud Creek (PM 8.9) from Thursday, May 31 and one aerial of Paul’s Slide from yesterday, June 3—courtesy of John Madonna

ED12B542-4DFC-4D78-9FEE-DA42DE34BF8EADFE97E7-CB89-4025-A58A-3ADEC5732EDD59FAF181-19C6-4C03-85B5-A1373E1F60F4

Highway Closure Update, 5/21/18

98F5BDEF-4BAE-4F10-9470-D22D8E143BE0

6CE267FD-39F4-4B14-A748-68C5E4495671

4528EB7F-E187-445A-80E0-60830F33AA34

Photos 1 and 2 of Mud Creek (PM 8.9) from Friday, May 18 and photo 3 of the repair at Hermitage (PM 22.42) last Monday, May 14 requiring Paul’s Slide area to be closed.

HIGHWAY 1 UPDATE – Monday, May 21

State Route 1 in Monterey County remains closed from north of Salmon Creek, just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek slide. State Route 1 south of Salmon Creek is accessible via State Route 1 in San Luis Obispo County near Ragged Point.

REMINDER: Travelers still CANNOT access the entire length of Highway 1 from Carmel to Cambria but local businesses are open on both sides of Mud Creek.

Mud Creek (PM 8.9)

Mud Creek had a major slide on Saturday, May 20, 2017, losing over 5 million cubic yards of material. Caltrans continues with its plan to realign the existing terrain. The Department has announced a new target of mid-September to get lanes re-opened to traffic. Caltrans will continuously evaluate the opening date as work progresses so we anticipate providing an update in July. It’s expected that even after the highway is re-open, intermittent lane closures and roadwork may continue. The updated current cost is at $54 million.

There is currently no public/local access through the Mud Creek area since this remains an active, emergency construction zone.

This week: Work continues with the north fill, north cut and north berm with hilfiker retaining wall.

Paul’s Slide (PM 21.6)*

Paul’s Slide is still active but the 24/7 traffic signal remains in place and temporary guardrail (k-rail) in the centerline. A full, daytime closure took place at Paul’s last Monday, May 14, 2018 to make repairs to the Hermitage Tieback Wall. (See attached photo).

ADDITIONAL WORK—CALPORTLAND PAVING BETWEEN LUCIA (PM 23) AND JUST SOUTH OF PCB (45.52)

Final items continue taking place. Metal Beam Guardrail (MBGR) end treatment work at Castro Canyon (PM 43.12) and slope work at the Coastlands (PM 44.41) continues taking place. However, no work is scheduled for this week north of Lucia.

The next update will be on Tuesday, May 29.

Highway One Closure Update, 5/14/18

This slideshow requires JavaScript.

SPECIAL NOTE: The full, daytime closure at Paul’s today, May 14, 2018 from 7 AM to 5 PM and is required due to equipment blocking the lane to make repairs to the Hermitage Tieback Wall. Paul’s should reopen by 5 PM on the same day, today, Monday, May 14.

HIGHWAY 1 UPDATE – Monday, May 14

State Route 1 in Monterey County remains closed from north of Salmon Creek, just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek slide. State Route 1 south of Salmon Creek is accessible via State Route 1 in San Luis Obispo County near Ragged Point.

REMINDER: Travelers still CANNOT access the entire length of Highway 1 from Carmel to Cambria but local businesses are open on both sides of Mud Creek.

 Mud Creek (PM 8.9)

Mud Creek had a major slide on Saturday, May 20, 2017, losing over 5 million cubic yards of material. Caltrans continues with its plan to realign the existing terrain. The Department has announced a new target of mid-September to get lanes re-opened to traffic. Caltrans will continuously evaluate the opening date as work progresses so we anticipate providing an update in July. It’s expected that even after the highway is re-open, intermittent lane closures and roadwork may continue. The updated current cost is at $54 million.

There is currently no public/local access through the Mud Creek area since this remains an active, emergency construction zone.

This week: Work continues with constructing the north fill and continue the north cut.

Paul’s Slide (PM 21.6)*

Paul’s Slide is still active but the 24/7 traffic signal remains in place and temporary guardrail (k-rail) in the centerline. A full, daytime closure at Paul’s is taking place today, Monday, May 14, 2018 from 7 AM to 5 PM and is required due to equipment blocking the lane to make repairs to the Hermitage Tieback Wall. Paul’s should reopen by 5pm on the same day, today, Monday, May 14.

Mud Creek Contract and other oddities, 5/5/18

Yesterday, I finally had the time to go through the Mud Creek contract first awarded to Madonna Construction on 1/19/17.  I’ve pulled out a few bits of information, took some screen shots, sent off emails to Cal Trans for comments, and otherwise started research and analysis. There is still much to discover and understand, but given that no one at Cal Trans has thus far responded, I decided to publish what I have today.

The original contract provided for removing slide material, installing rock nets, and restoring facilities to enable reopening the highway. This contract was awarded 1/19/17 and signed 3/17/17. It was for 30 days at a cost of $2,500,000. It is a public works contract specifically excluded from 2 CCR § 547.59. (California Code of Regulations.) It is exempt from public bidding as explained in the State Contracts Manual (SCM) §5.80 (A)(3) which states: “As noted in section 5.05, competitive bidding is required unless there is a legally authorized basis for bid exemption. Key exemption categories are identified below. A. Statutory Exemptions: 3. Emergency contracts. The work or service is for the immediate preservation of the public health, welfare, safety, or protection of State property (PCC §§ 1102, 10340).”

On 4/6/17, the original contract was modified to increase the contract from $2,500,000 to $9,500,000 an increase of 3 and 1/2 times the original amount and added 80 days for completion, for a total of 110 days. After the BIG slide on 5/19/17, The Contract was again modified two months later on 7/18/17 to $12,000,000 and another 60 days was added to the contract for a total of 170 days. Two more modifications, one on 9/20/17 for an additional amount of $32,000,000 and an addition of 150 WORKING days (30 weeks) for a total of 320 days, and another on 9/18/17 of total amount of $56,000,000 (previously awarded, PLUS the requested additional $32,000,000) would then take the contract to the end of April 2018.

D13D1E24-161A-4FBA-A6E1-588888080E12

B4642B53-C192-4AAD-8A15-3EB699BEEC1C

By my calculations, the time and the $56,000,000 award ran out on 4/18/18 although the first page reproduced above says “end of April” so the contract has been renewed or is in the process of being renewed. I asked for the extension on this contract, but have yet to receive it. I will discuss it when received and will follow-up on that next week.

Besides the contract itself, I also inquired about the excavation going on at Grey Slip, a few miles south of Mud Creek, to obtain fill material. Grey Slip is another area of prior road issues.  I asked Cal Trans to comment on this yesterday, but so far have not received any response. One local was told that they had originally started excavation on the west side, but after some movement, moved to the east. I have not been able to confirm this, as Cal Trans did not respond to my questions. I looked through some of my photographs to see if I could find an older one to show any prior issues at this point, but haven’t been able to locate one. Rock Knocker put all his old photos in a storage unit in Paso/Templeton, so no help there. If anyone else has a photo of Grey Slip in prior years, I would love to see it.

This is what is happening at Grey Slip currently:

B6C4E6B6-12F4-475D-A467-369357D3C59CDC90ABA3-1C5F-4EF6-AA8F-0C20571382E5

 

 

Road Widening between Bixby & Rocky?

Anyone seen this sign and know what is going on? Sent to me by Ken Ekelund:

1F3E836D-0F4D-444F-A9EC-81CD20352C90

Here is the original project description document:

http://www.dot.ca.gov/dist05/projects/hurricane_point.pdf

Highway Closure Update, 4/24/18

Photos (1-2) of Mud Creek (PM 8.9) from Friday, April 20; (3-5) of the Coastlands (PM 44.41) south of PCB taken Friday, April 20, pictures of “Geo Web” before and after being covered up by soil—it helps stabilize the slope.

HIGHWAY 1 UPDATE – Tuesday, April 24

State Route 1 in Monterey County remains closed from north of Salmon Creek, just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek slide. State Route 1 south of Salmon Creek is accessible via State Route 1 in San Luis Obispo County near Ragged Point.

REMINDER: Travelers still CANNOT access the entire length of Highway 1 from Carmel to Cambria but local businesses are open on both sides of Mud Creek.

Mud Creek (PM 8.9)

Mud Creek had a major slide on Saturday, May 20, 2017, losing over 5 million cubic yards of material. Caltrans continues with its plan to realign the existing terrain with the projected timeline to safely open to public traffic is late-summer 2018 at an estimated cost of $40 million. A more specific opening schedule will be announced in next week’s update.

This week: Work continues on the north cut, middle and north fills, and on north berm.

 There is currently no public/local access through the Mud Creek area since this remains an active, emergency construction zone.

 Paul’s Slide (PM 21.6)

Paul’s Slide was cleaned up last week from debris and slide material. It is still active but the 24/7traffic signal remains in place and temporary guardrail (k-rail) in the centerline.

ADDITIONAL WORK—CALPORTLAND PAVING BETWEEN LUCIA (PM 23) AND JUST SOUTH OF PCB (45.52)

Final items continue taking place. Metal Beam Guardrail (MBGR) end treatment work at Castro Canyon (PM 43.12) and slope work at the Coastlands (PM 44.41) is taking place. Last week Geo Web was installed to help stabilize the slope (see pix above). This week we are adding recessed marker to the striping.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

The next update will be on Monday, April 30

Susana Z. Cruz

Caltrans District 5

Public Information Officer