Highway One Closure Update, 1/22/18

81F81454-0FB5-4502-8AC5-51ACD473C63E8983A63F-24CB-4747-BED4-65F5F70D0D45A11AF4B6-5EC5-4965-A2A2-106BE0FBBDA0

Photos of Mud Creek (PM 8.9), 1 and 2 show the installation of the 24-inch culvert at the southern end of the job; photo 3 shows work on the northern end.

HIGHWAY 1 UPDATE – Monday, Jan. 8, 2018
State Route 1 in Monterey County remains closed from north of Salmon Creek, just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek slide. State Route 1 south of Salmon Creek is accessible via State Route 1 in San Luis Obispo County near Ragged Point.

REMINDER: Travelers still CANNOT access the entire length of Highway 1 from Carmel to Cambria but local businesses are open on both sides of Mud Creek.

Mud Creek (PM 8.9)
Mud Creek had a major slide on Saturday, May 20, 2017, losing over 5 million cubic yards of material. Caltrans continues with its plan to realign the existing terrain with the projected timeline to safely open to public traffic is late-summer 2018 at an estimated cost of $40 million.

Last week, the contractor continued with north fill and the mud creek drainage, installing a 24-inch culvert at the southern end of the job. This week, the contractor continues working on the north fill at the northern flank of the slide, enhancing the revetment across the toe of the slide to increase the height of the rock, trucking, moving, and placing rock, and installation and fabrication of drainage features like welded HDPE pipe, concrete drainage inlets, etc. From a monitoring perspective, we continue to work with Surveys to remotely read prism positions on the landslide, manually measure movement using extensometers and distances between known positions, and making frequent visual observations.

There is currently no public/local access through the Mud Creek area since this remains an active, emergency construction zone.

Paul’s Slide (PM 21.6)
Paul’s Slide is still active but the 24/7 traffic signal remains in place and temporary guardrail (k-rail) in the centerline.

Pfeiffer Canyon Bridge [PCB] (PM 45.52)
1.) Final work continues for two additional weeks. Roadwork at Pfeiffer Canyon Bridge consists of alternating lane closures from 7 am to 4 pm Mondays through Thursdays and 7 am to 2 pm on Fridays until work is complete. Last week fog sealing and other final items took place. This week, structure punch list items, installation of seismic monitoring, backing of AC Dike, project cleanup, grading of the project yard, demobilization of equipment and materials (except equipment necessary to install Flange Protection), and hand seeding of areas disturbed by recent work will take place. All work is expected to be complete at the end of next week (end of January), weather permitting.

ADDITIONAL WORK—CALPORTLAND PAVING BETWEEN LUCIA (PM 23) AND JUST SOUTH OF PCB (45.52)
This week: Paving continues from the gas station/Post office (4