Two hard, full overnight closures at Rocky Creek next week

Today’s Date: Wednesday, April 10, 2013 at 3:15 pm
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa
Cruz Counties
Contact: Susana Z Cruz (bilingual) or Colin Jones
Phone: (805) 549-3138 or 549-3189
FOR IMMEDIATE RELEASE

** UPDATE #26 **
HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT CONTINUES WITH DAYTIME ROADWORK AND INTERMITTENT OVERNIGHT CLOSURES

Daytime roadwork on Highway 1 at Rocky Creek continues next week from 7 am to 5 pm Monday, April 15 through Friday, April 19.

Night work will be as follows:
Tuesday, April 16 from 7 pm to 9 pm—temporary closures with up to 10-minute delays;

Night work being done consists of pouring concrete on the bridge deck off the highway.

Overnight work will be as follows:
Tuesday, April 16 from 9 pm to 7 am (Wednesday)–full closure in place;
Wednesday, April 17 from 11 pm to 7 am (Thursday)—full closure in place;

Overnight work being done consists of pouring concrete on the bridge deck on the highway and requires a full closure of the work zone. An update will be provided should the closure schedule change.

NOTE: No overnight closures Sunday, April 14, Monday, April 15, or Thursday, April 18.