Highway to open tomorrow, Weds. 7/18 at 10 am

CALTRANS
Today’s Date: Tuesday, July 17, 2018 at 1:30 pm
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa Cruz Counties                                                  
Contact:  Susana Z. Cruz (bilingual) or Colin Jones
FOR IMMEDIATE RELEASE                     
###TRAFFIC ADVISORY###
STATE ROUTE 1/MUD CREEK WILL OPEN TOMORROW, WEDNESDAY, JULY 18 BY 10 AM
 
MONTEREY COUNTY– The contractor made great progress in the last several days so final striping and inspection by our crews is underway. As a result, Highway 1 at Mud Creek will RE-OPEN by 10 am tomorrow, Wednesday, July 18, nearly 14 months after the massive landslide and emergency repair project.
 
Electronic Message Signs will be changed once the highway is open, also Headquarters Communications and QuickMap will be updated.
 
Our official ribbon-cutting/community celebration remains set for Friday, July 20 at 11 am at the Ragged Point Inn.
 
This $54 million repair included the reconstruction of ¼-mile of new roadway alignment built on the slide material and a compacted embankment at the south and north ends. The new highway extends out towards the ocean upwards of 250 from the original highway. The roadway is 150 to 260 feet above sea level and buttressed with a series of embankments, berms, rocks, netting, culverts and other stabilizing material.
 
IMPORTANT NOTE: All roadwork is still not complete at Mud Creek. Travelers may encounter one-way traffic control at times when a lane closure is needed, mostly on weekdays. Also, due to the cuts and work on the embankment and roadway at Mud Creek, it will take about two winters for the new slopes to fully stabilize.
 
The public may learn more about this and other projects by visiting the Caltrans District 5 News Release page at: http://dot.ca.gov/dist05/paffairs/release.htm.
 
 
Aerial photo of Mud Creek from today courtesy of John Madonna.
0C3565E6-31D7-4290-B5D7-8908D679A413

Photo Sunday, 7/15/18

Here are some old (1981) photos of Gray Slip. Some of the material for Mud Creek reconstruction came from here. We will be watching this one this winter, along, of course, with Mud Creek and Paul’s Slide. There are 10, I think, so going with a slide show this Sunday. May you have a peaceful Sunday…

This slideshow requires JavaScript.

Mud Creek Closure

NOTE: THE SOUTHERN CLOSURE ON STATE ROUTE 1 WILL MOVE FROM SALMON CREEK TO RAGGED POINT ON THE MORNING OF MONDAY, JULY 9 AND CONTINUE FOR MUCH OF THAT WEEK.

THE CLOSURE WILL MOVE BCK TO SALMON CREEK LATE IN THE DAY ON FRIDAY, JULY 13 UNTIL THE HIGHWAY IS FULLY OPENED.

Mud Creek is still scheduled to open July 20, 2018 with a ribbon cutting at Ragged Point at 11 am.

 

Cal Trans announces opening date of Mud Creek

Today’s Date:  Tuesday, July 3, 2018

District:     05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa

Cruz Counties

Contact:                                  Jim Shivers or Colin Jones

Phone:                                   (805) 549-3237 or 549-3189

FOR IMMEDIATE RELEASE                                                                                

CALTRANS ANNOUNCES PLAN TO RE-OPEN STATE ROUTE 1 AT MUD CREEK AFTERMASSIVE LANDSLIDE

Highway Opening Set for July 20 Restores Full Access to the Big Sur Coast

MONTEREY COUNTY–Caltrans has announced that State Route 1 at Mud Creek along the southern Big Sur Coast is scheduled to re-open by Friday, July 20 at 11 am.

A ribbon-cutting ceremony for the opening will take place at the Ragged Point Inn at that time.

The re-opening of this section of State Route 1 follows a massive landslide on May 20, 2017 which resulted in the movement of six million cubic yards of material and 50 acres of displaced land, including the creation of 2,400 feet of new shoreline. A quarter-mile section of roadway was lost due to this landslide.

“We’re very pleased to share this long-awaited news with everyone who travels along this international destination the many businesses that benefit from the coast highway,” said Caltrans Director Laurie Berman. “Mud Creek is the last closure point so travelers will be able to take Highway 1 all the way through Big Sur for the first time in 18 months.

This section of State Route 1 was built across the slide material buttressed with a series of embankments and compacted soil and using protective features including berms, rocks, netting, culverts and other stabilizing material.

The rebuilding effort included construction seven days a week, dawn to dusk for the past year and was completed two months ahead of our initial mid-September estimate.

The contractor for this $54 million emergency project was John Madonna Construction of San Luis Obispo, CA.

For traffic updates on all state highways in San Luis Obispo County, motorists may call Caltrans District 5 Public Affairs at 805-549-3318 or visit: http://www.dot.ca.gov/dist05/road_information.htm.

 

###

 

 

 

 

Highway 1 at Mud Creek near Gorda looking south (7/2/18, photo courtesy of Caltrans)

Mud Creek Photos, cont.

I don’t have Rock Knocker to provide his running commentary on these, but here they are anyway. Since there are 20 of them, I put them into a slide show.

This slideshow requires JavaScript.

No Parking NB Highway 1 at Point Lobos

For Immediate Release Contact: Maia Carroll, Communications Coordinator

June 27, 2018
No Parking Signs Added Near Pt. Lobos for Emergency Vehicle Access
‘No Parking’ signs will be installed this week along northbound Highway 1 near Point Lobos to allow better access for emergency vehicles while traffic is impacted by construction at the Highway 1 Climbing Lane project at Rio Road in Carmel. Parking will still be allowed along southbound Highway 1 near Point Lobos.
Maintaining emergency access is particularly important as the 4th of July holiday approaches and there are more travelers not only on the roadways but at nearby beaches where emergency calls are routine this time of year.
Work crews will place signage June 28th and 29th on the east side of Highway 1 along the shoulder 1,800 feet to the north and south of the entrance to Pt. Lobos State Park. This additional signage does not affect entrance to the park. However, with limited parking within the Natural Reserve, visitors are encouraged to consider exploring one of the numerous other state, county and regional parks and beaches in Monterey County.
###

More Highway One bad news? 6/27/18

6/28 UPDATE: I checked with Cal Trans re this, and as a reader noted below in the comments, this is not new. CT replied:

”Yes, the bridge is fine.  It’s the Dolan Creek Bridge and it’s been like that for quite a while.  It has been inspected numerous times.  Heath said that the bridge crew checked it not too long ago.  It was apparently a newer CHP officer that noticed it, but I’m glad he’s looking for those kinds of things.

I can only hope this is found to be nothing, although it sounds potentially disastrous. (thanks for pointing this out, Jeff Mallory)

incident: 00193 Type: Request CalTrans Notify
Location: 3160 MM1 Loc Desc: SR1 X DOLAN CREEK BRIDGE
Lat/Lon: 36.111418 -121.627833
Detail Information
3:06 PM 3 [6] [Notification] [CHP]-CAL TRANS ENRT, 20 MIN ETA
2:45 PM 2 [2] 1039 CT
2:42 PM 1 [1] CT SUPERVISOR TO RESPOND TO DOLAN CREEK BRIDGE MM 31.6 // NOTICIABLE SAG IN SB LANE NORTHERN MOST PART OF BRIDGE

Highway One Closure Update, 6/25/18

Nothing new to report re Mud Creek and Paul’s Slide, and the photos show nothing new re Mud Creek, but here are a couple from the scaling operation at Paul’s Slide on Friday.

51D6F90D-0C2E-44D0-803A-3BE639F8614E838324C6-642A-49DA-BE36-8CA5FD6282C7

Photo Sunday, 6/24/18 – Mud Creek

All photos by Rock Knocker, taken on Friday, 6/23/18. I’ll add more with explanations later but here are a few, one can tell it is still draining and still moving…more later. Thank you Cal Trans, Susana Cruz and Wayne Walker in particular, for helping to arrange this pre-opening tour.

50A9B433-5EF5-498B-897D-B54AF7B423EEED401376-BFDB-44C4-8E73-FA7D8B7BA149D0527001-84AA-4225-840D-7BF05CDFFA16

FCC6C07E-BD4E-454F-904F-D7BA8CB144E7